IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

61

matching recommendations
Reset
SIC 27 Printing And Publishing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NV0127 # 04 Y:1999 04 1999 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,768 $588 Implemented
NV0127 # 05 Y:1999 05 1999 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $375 $64 Not Implemented
NV0127 # 10 Y:1999 10 1999 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $1,343 $325 Implemented
NV0127 # 09 Y:1999 09 1999 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $1,890 $0 Not Implemented
NV0127 # 06 Y:1999 06 1999 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $704 $80 Not Implemented
NV0127 # 07 Y:1999 07 1999 INSTALL SKYLIGHTS $1,727 $3,945 Not Implemented
NV0123 # 05 Y:1999 05 1999 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $500,000 $3,070,000 Not Implemented
NV0123 # 04 Y:1999 04 1999 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $331 $170 Not Implemented
NV0123 # 06 Y:1999 06 1999 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $23,949 $164,000 Not Implemented
NV0123 # 03 Y:1999 03 1999 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,829 $800 Not Implemented
NV0123 # 02 Y:1999 02 1999 USE RADIANT HEATER FOR SPOT HEATING $2,445 $4,015 Not Implemented
NV0123 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,202 $4,519 Not Implemented
NV0117 # 03 Y:1998 03 1998 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $4,032 $1,000 Implemented
NV0117 # 01 Y:1998 01 1998 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $242 $252 Implemented
NV0117 # 02 Y:1998 02 1998 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $25,175 $82,000 Implemented
NV0044 # 04 Y:1995 04 1995 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $903 $911 Not Implemented
NV0044 # 05 Y:1995 05 1995 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $2,151 $4,335 Implemented
NV0044 # 03 Y:1995 03 1995 INSTALL OCCUPANCY SENSORS $1,544 $736 Not Implemented
NV0044 # 02 Y:1995 02 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,457 $978 Implemented
NV0044 # 01 Y:1995 01 1995 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $2,702 $175 Implemented
NV0015 # 06 Y:1994 06 1994 INSTALL OCCUPANCY SENSORS $1,632 $341 Not Implemented
NV0015 # 05 Y:1994 05 1994 USE PHOTOCELL CONTROLS $170 $0 Not Implemented
NV0015 # 04 Y:1994 04 1994 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $734 $120 Implemented
NV0015 # 03 Y:1994 03 1994 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $323 $0 Not Implemented
NV0015 # 02 Y:1994 02 1994 OPTIMIZE PLANT POWER FACTOR $1,726 $6,150 Not Implemented