Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,640
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0084 # 01 Y:1983 | 01 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,386 | $127 | Not Implemented |
KU0084 # 02 Y:1983 | 02 | 1983 | INSTALL TIMERS AND/OR THERMOSTATS | $3,551 | $1,400 | Not Implemented |
KU0084 # 03 Y:1983 | 03 | 1983 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $877 | $155 | Implemented |
KU0084 # 04 Y:1983 | 04 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $167 | $160 | Implemented |
KU0084 # 05 Y:1983 | 05 | 1983 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $135 | $0 | Not Implemented |
KU0084 # 06 Y:1983 | 06 | 1983 | INSTALL AUTOMATIC STACK DAMPER | $84 | $144 | Not Implemented |
KU0070 # 01 Y:1983 | 01 | 1983 | REDUCE VENTILATION AIR | $68,280 | $2,361 | Not Implemented |
KU0070 # 02 Y:1983 | 02 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,139 | $1,900 | Not Implemented |
KU0070 # 03 Y:1983 | 03 | 1983 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $8,631 | $5,200 | Not Implemented |
KU0070 # 04 Y:1983 | 04 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,046 | $3,942 | Not Implemented |
KU0070 # 05 Y:1983 | 05 | 1983 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $1,975 | $13,000 | Implemented |
KU0070 # 06 Y:1983 | 06 | 1983 | OPTIMIZE PLANT POWER FACTOR | $3,510 | $5,820 | Not Implemented |
KU0070 # 07 Y:1983 | 07 | 1983 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $664 | $42 | Implemented |
KU0070 # 08 Y:1983 | 08 | 1983 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $615 | $0 | Not Implemented |
KU0070 # 09 Y:1983 | 09 | 1983 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $502 | $72 | Not Implemented |
KU0079 # 01 Y:1983 | 01 | 1983 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $4,862 | $0 | Not Implemented |
KU0079 # 02 Y:1983 | 02 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,477 | $1,800 | Not Implemented |
KU0079 # 03 Y:1983 | 03 | 1983 | IMPROVE LUBRICATION PRACTICES | $1,453 | $300 | Not Implemented |
KU0079 # 04 Y:1983 | 04 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $520 | $350 | Not Implemented |
KU0079 # 05 Y:1983 | 05 | 1983 | INSTALL AUTOMATIC STACK DAMPER | $417 | $275 | Implemented |
KU0079 # 06 Y:1983 | 06 | 1983 | OPTIMIZE PLANT POWER FACTOR | $376 | $425 | Not Implemented |
KU0079 # 07 Y:1983 | 07 | 1983 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $250 | $220 | Not Implemented |
KU0079 # 08 Y:1983 | 08 | 1983 | INSTALL AUTOMATIC STACK DAMPER | $67 | $90 | Implemented |
KU0079 # 09 Y:1983 | 09 | 1983 | INCREASE AMOUNT OF CONDENSATE RETURNED | $623 | $0 | Implemented |
UD0075 # 01 Y:1983 | 01 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,287 | $562 | Not Implemented |