Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,640
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0695 # 07 Y:2015 | 07 | 2015 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,350 | $540 | Implemented |
AM0695 # 08 Y:2015 | 08 | 2015 | INSTALL OCCUPANCY SENSORS | $150 | $170 | Not Implemented |
OK0928 # 01 Y:2015 | 01 | 2015 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $21,773 | $7,320 | Implemented |
OK0928 # 02 Y:2015 | 02 | 2015 | INSTALL SET-BACK TIMERS | $2,950 | $972 | Implemented |
OK0928 # 03 Y:2015 | 03 | 2015 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $149 | $132 | Implemented |
OK0928 # 04 Y:2015 | 04 | 2015 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $9,143 | $18,884 | Not Implemented |
OK0928 # 05 Y:2015 | 05 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $988 | $2,440 | Not Implemented |
OK0928 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,832 | $38,110 | Implemented |
OK0928 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,758 | $25,753 | Implemented |
OK0928 # 08 Y:2015 | 08 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,204 | $5,149 | Implemented |
OK0928 # 09 Y:2015 | 09 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,212 | $863 | Implemented |
OK0928 # 10 Y:2015 | 10 | 2015 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $6,912 | $5,775 | Not Implemented |
OK0928 # 11 Y:2015 | 11 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $35,000 | $70,000 | Implemented |
OK0928 # 12 Y:2015 | 12 | 2015 | OPTIMIZE PLANT POWER FACTOR | $2,621 | $20,000 | Not Implemented |
OK0928 # 13 Y:2015 | 13 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $581 | $468 | Not Implemented |
IP0050 # 01 Y:2015 | 01 | 2015 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,927 | $0 | Implemented |
IP0050 # 02 Y:2015 | 02 | 2015 | INSTALL TIMERS AND/OR THERMOSTATS | $3,405 | $163 | Implemented |
IP0050 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,187 | $1,400 | Implemented |
IP0050 # 04 Y:2015 | 04 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $666 | $543 | Implemented |
IP0050 # 05 Y:2015 | 05 | 2015 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $2,184 | $1,792 | Not Implemented |
IP0050 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,242 | $4,203 | Implemented |
IP0050 # 07 Y:2015 | 07 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,348 | $5,370 | Implemented |
IP0050 # 08 Y:2015 | 08 | 2015 | OPTIMIZE PLANT POWER FACTOR | $10,314 | $19,140 | Not Implemented |
IP0050 # 09 Y:2015 | 09 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,085 | $21,918 | Not Implemented |
MZ0171 # 01 Y:2015 | 01 | 2015 | AIR CONDITION ONLY SPACE NECESSARY | $1,588 | $0 | Not Implemented |