Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
314
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0437 # 07 Y:2013 | 07 | 2013 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $28,111 | $46,338 | Not Implemented |
SF0437 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,497 | $14,135 | Implemented |
SF0437 # 05 Y:2013 | 05 | 2013 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $354 | $1,395 | Not Implemented |
SF0437 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $425 | $729 | Implemented |
SF0437 # 03 Y:2013 | 03 | 2013 | INSTALL OCCUPANCY SENSORS | $3,792 | $6,796 | Implemented |
SF0437 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $620 | $0 | Not Implemented |
SF0437 # 01 Y:2013 | 01 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $911 | $0 | Implemented |
SF0373 # 06 Y:2009 | 06 | 2009 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $402 | $906 | Implemented |
SF0373 # 05 Y:2009 | 05 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $765 | $1,569 | Not Implemented |
SF0373 # 04 Y:2009 | 04 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $335 | $553 | Implemented |
SF0373 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $1,227 | $1,320 | Implemented |
SF0373 # 02 Y:2009 | 02 | 2009 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,700 | $3,605 | Implemented |
SF0373 # 08 Y:2009 | 08 | 2009 | USE SOLAR HEAT TO MAKE ELECTRICTY | $32,866 | $534,450 | Not Implemented |
SF0373 # 01 Y:2009 | 01 | 2009 | REPAIR AND ELIMINATE STEAM LEAKS | $1,103 | $0 | Implemented |
SF0373 # 07 Y:2009 | 07 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,543 | $12,880 | Implemented |
LM0107 # 06 Y:2006 | 06 | 2006 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $20,251 | $1,000 | Implemented |
LM0107 # 05 Y:2006 | 05 | 2006 | ADOPT IN-HOUSE MATERIAL GENERATION | $16,864 | $1,000 | Implemented |
LM0107 # 04 Y:2006 | 04 | 2006 | DEVELOP STANDARD OPERATING PROCEDURES | $178,334 | $5,400 | Implemented |
LM0107 # 03 Y:2006 | 03 | 2006 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $225,208 | $12,980 | Implemented |
LM0107 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,219 | $2,200 | Implemented |
LM0107 # 01 Y:2006 | 01 | 2006 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,522 | $2,400 | Not Implemented |
SF0307 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $268 | $653 | Implemented |
SF0307 # 03 Y:2005 | 03 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,884 | $4,039 | Not Implemented |
SF0307 # 02 Y:2005 | 02 | 2005 | INSTALL OCCUPANCY SENSORS | $1,962 | $3,472 | Not Implemented |
SF0307 # 01 Y:2005 | 01 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,571 | $0 | Implemented |