Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,892
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0145 # 11 Y:1984 | 11 | 1984 | INSTALL TURBULATORS | $1,274 | $1,200 | Not Implemented |
KU0145 # 12 Y:1984 | 12 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $2,255 | $2,000 | Not Implemented |
KU0145 # 13 Y:1984 | 13 | 1984 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $847 | $250 | Implemented |
KU0145 # 14 Y:1984 | 14 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $134 | $350 | Implemented |
KU0145 # 15 Y:1984 | 15 | 1984 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,262 | $3,348 | Not Implemented |
KU0145 # 16 Y:1984 | 16 | 1984 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $299 | $0 | Implemented |
KU0145 # 17 Y:1984 | 17 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,440 | $159 | Not Implemented |
KU0145 # 18 Y:1984 | 18 | 1984 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $352 | $0 | Implemented |
TN0223 # 01 Y:1984 | 01 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $18,629 | $12,000 | Implemented |
TN0223 # 02 Y:1984 | 02 | 1984 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $11,022 | $792 | Implemented |
TN0223 # 03 Y:1984 | 03 | 1984 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $5,685 | $8,880 | Not Implemented |
TN0223 # 04 Y:1984 | 04 | 1984 | USE MINIMUM STEAM OPERATING PRESSURE | $908 | $0 | Not Implemented |
TN0223 # 05 Y:1984 | 05 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,013 | $0 | Implemented |
TN0223 # 06 Y:1984 | 06 | 1984 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,336 | $0 | Not Implemented |
TN0223 # 07 Y:1984 | 07 | 1984 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $966 | $0 | Not Implemented |
TN0223 # 08 Y:1984 | 08 | 1984 | INSTALL / REPAIR INSULATION ON STEAM LINES | $305 | $133 | Implemented |
TN0210 # 01 Y:1984 | 01 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,637 | $100 | Implemented |
TN0210 # 02 Y:1984 | 02 | 1984 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,764 | $2,000 | Implemented |
TN0210 # 03 Y:1984 | 03 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $879 | $2,780 | Not Implemented |
TN0210 # 04 Y:1984 | 04 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $189 | $70 | Implemented |
TN0210 # 05 Y:1984 | 05 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $246 | $20 | Implemented |
KU0117 # 01 Y:1984 | 01 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,895 | $15,000 | Not Implemented |
KU0117 # 02 Y:1984 | 02 | 1984 | INSTALL TURBULATORS | $4,977 | $2,620 | Not Implemented |
KU0117 # 03 Y:1984 | 03 | 1984 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,455 | $300 | Not Implemented |
KU0117 # 04 Y:1984 | 04 | 1984 | REPAIR OR REPLACE STEAM TRAPS | $18,415 | $4,200 | Implemented |