Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
216
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1089 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,974 | $0 | n/a |
UD1089 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $472 | $550 | n/a |
UD1089 # 02 Y:2024 | 02 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $30,384 | $0 | n/a |
UD1089 # 06 Y:2024 | 06 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,228 | $27,650 | n/a |
UD1089 # 01 Y:2024 | 01 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $79,860 | $0 | n/a |
UD1089 # 04 Y:2024 | 04 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $7,169 | $2,030 | n/a |
UU0255 # 07 Y:2024 | 07 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,849 | $4,680 | n/a |
UU0255 # 02 Y:2024 | 02 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $5,674 | $8,711 | n/a |
UU0255 # 04 Y:2024 | 04 | 2024 | USE OPTIMUM THICKNESS INSULATION | $10,948 | $4,085 | n/a |
UU0255 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,033 | $8,000 | n/a |
UU0255 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $1,750 | $4,964 | n/a |
UU0255 # 01 Y:2024 | 01 | 2024 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $64,548 | $8,000 | n/a |
UU0255 # 03 Y:2024 | 03 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,299 | $2,614 | n/a |
UU0255 # 08 Y:2024 | 08 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,932 | $60,862 | n/a |
MI0445 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $32,574 | $11,027 | n/a |
MI0445 # 06 Y:2024 | 06 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $19,584 | $150 | n/a |
MI0445 # 08 Y:2024 | 08 | 2024 | INSTALL OCCUPANCY SENSORS | $3,269 | $2,860 | n/a |
MI0445 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $46,588 | $99,444 | n/a |
MI0445 # 02 Y:2024 | 02 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $217,248 | $42,472 | n/a |
MI0445 # 01 Y:2024 | 01 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $427,475 | $602,500 | n/a |
MI0445 # 03 Y:2024 | 03 | 2024 | PAY UTILITY BILLS ON TIME | $80,165 | $0 | n/a |
MI0445 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,583 | $5,793 | n/a |
OR0791 # 02 Y:2024 | 02 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,032 | $0 | n/a |
OR0791 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $2,606 | $17,324 | n/a |
OR0791 # 04 Y:2024 | 04 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,079 | $5,750 | n/a |