IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

18

matching recommendations
Reset
SIC 2851 Paints And Allied Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WM0225 # 05 Y:2024 05 2024 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,246 $1,375 n/a
WM0225 # 04 Y:2024 04 2024 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $3,687 $4,037 n/a
WM0225 # 03 Y:2024 03 2024 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,067 $5,244 n/a
WM0225 # 02 Y:2024 02 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $25,176 $0 n/a
WM0225 # 01 Y:2024 01 2024 PREHEAT COMBUSTION AIR WITH WASTE HEAT $43,885 $200,000 n/a
WM0130 # 10 Y:2019 10 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $698 $1,050 Not Implemented
WM0130 # 13 Y:2019 13 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $154 $255 Not Implemented
WM0130 # 12 Y:2019 12 2019 USE PHOTOCELL CONTROLS $175 $404 Not Implemented
WM0130 # 11 Y:2019 11 2019 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $597 $1,513 Not Implemented
WM0130 # 01 Y:2019 01 2019 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $18,300 $26,000 Not Implemented
WM0130 # 09 Y:2019 09 2019 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $705 $315 Not Implemented
WM0130 # 08 Y:2019 08 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,212 $800 Not Implemented
WM0130 # 07 Y:2019 07 2019 USE SYNTHETIC LUBRICANT $1,417 $497 Not Implemented
WM0130 # 06 Y:2019 06 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,815 $4,154 Not Implemented
WM0130 # 05 Y:2019 05 2019 OPTIMIZE PLANT POWER FACTOR $2,616 $3,000 Not Implemented
WM0130 # 04 Y:2019 04 2019 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $5,515 $690 Not Implemented
WM0130 # 03 Y:2019 03 2019 USE SOLAR HEAT TO MAKE ELECTRICTY $13,760 $48,500 Not Implemented
WM0130 # 02 Y:2019 02 2019 REPAIR OR REPLACE STEAM TRAPS $15,350 $11,500 Not Implemented