Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
19
matching recommendationsSIC | 2952 | Asphalt Felts And Coatings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1002 # 07 Y:2019 | 07 | 2019 | USE RADIANT HEATER FOR SPOT HEATING | $39,703 | $37,000 | Not Implemented |
OK1002 # 06 Y:2019 | 06 | 2019 | INSTALL SET-BACK TIMERS | $1,083 | $802 | Implemented |
OK1002 # 05 Y:2019 | 05 | 2019 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $191,600 | $806,420 | Not Implemented |
OK1002 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,768 | $3,646 | Implemented |
OK1002 # 03 Y:2019 | 03 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,400 | $2,933 | Implemented |
OK1002 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,343 | $2,609 | Implemented |
OK1002 # 01 Y:2019 | 01 | 2019 | OPTIMIZE PLANT POWER FACTOR | $20,293 | $28,306 | Not Implemented |
AR0010 # 02 Y:1993 | 02 | 1993 | REPAIR AND ELIMINATE STEAM LEAKS | $8,251 | $1,400 | Implemented |
AR0010 # 05 Y:1993 | 05 | 1993 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,412 | $30 | Implemented |
AR0010 # 04 Y:1993 | 04 | 1993 | INSULATE BARE EQUIPMENT | $85,106 | $13,998 | Not Implemented |
AR0010 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,539 | $16,518 | Implemented |
AR0010 # 01 Y:1993 | 01 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,459 | $1,483 | Implemented |
LT0024 # 04 Y:1985 | 04 | 1985 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $836 | $0 | Implemented |
LT0024 # 05 Y:1985 | 05 | 1985 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $2,010 | $300 | Implemented |
LT0024 # 06 Y:1985 | 06 | 1985 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,430 | $2,170 | Implemented |
LT0024 # 07 Y:1985 | 07 | 1985 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $449 | $379 | Not Implemented |
LT0024 # 03 Y:1985 | 03 | 1985 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $4,160 | $1,930 | Not Implemented |
LT0024 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $12,930 | $0 | Implemented |
LT0024 # 01 Y:1985 | 01 | 1985 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,263 | $642 | Implemented |