Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
45
matching recommendationsSIC | 299 | Misc. Petroleum And Coal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0207 # 02 Y:1986 | 02 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,525 | $0 | Implemented |
KU0207 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,480 | $0 | Implemented |
KU0207 # 04 Y:1986 | 04 | 1986 | INSTALL SET-BACK TIMERS | $9,165 | $1,494 | Implemented |
KU0207 # 05 Y:1986 | 05 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,099 | $12,675 | Not Implemented |
KU0207 # 06 Y:1986 | 06 | 1986 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $5,637 | $6,030 | Implemented |
KU0207 # 07 Y:1986 | 07 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $2,817 | $52 | Implemented |
KU0207 # 08 Y:1986 | 08 | 1986 | ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE | $1,802 | $0 | Not Implemented |
KU0207 # 09 Y:1986 | 09 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,433 | $0 | Implemented |
KU0207 # 10 Y:1986 | 10 | 1986 | INSTALL STEAM TRAP | $600 | $90 | Not Implemented |
KU0207 # 11 Y:1986 | 11 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $547 | $0 | Implemented |
KU0207 # 12 Y:1986 | 12 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $516 | $150 | Implemented |
KU0207 # 13 Y:1986 | 13 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $469 | $0 | Implemented |
KU0104 # 01 Y:1983 | 01 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,312 | $1,500 | Implemented |
KU0104 # 08 Y:1983 | 08 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $759 | $1,026 | Implemented |
KU0104 # 07 Y:1983 | 07 | 1983 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,308 | $132 | Implemented |
KU0104 # 06 Y:1983 | 06 | 1983 | INSTALL / REPAIR INSULATION ON STEAM LINES | $9,791 | $5,000 | Implemented |
KU0104 # 05 Y:1983 | 05 | 1983 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $916 | $800 | Implemented |
KU0104 # 04 Y:1983 | 04 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,624 | $400 | Implemented |
KU0104 # 03 Y:1983 | 03 | 1983 | REPAIR OR REPLACE STEAM TRAPS | $2,673 | $2,000 | Implemented |
KU0104 # 02 Y:1983 | 02 | 1983 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $2,960 | $800 | Implemented |