Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,355
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0326 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $440 | $0 | n/a |
IC0326 # 04 Y:2025 | 04 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,819 | $678 | n/a |
IC0326 # 08 Y:2025 | 08 | 2025 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $15,398 | $114,881 | n/a |
IC0326 # 10 Y:2025 | 10 | 2025 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $93 | $0 | n/a |
IC0326 # 05 Y:2025 | 05 | 2025 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $393 | $1,089 | n/a |
IC0326 # 06 Y:2025 | 06 | 2025 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $657 | $3,632 | n/a |
IC0326 # 07 Y:2025 | 07 | 2025 | INSULATE BARE EQUIPMENT | $2,266 | $2,982 | n/a |
IC0326 # 01 Y:2025 | 01 | 2025 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $9,345 | $13,327 | n/a |
IC0326 # 03 Y:2025 | 03 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,821 | $4,859 | n/a |
IC0326 # 09 Y:2025 | 09 | 2025 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $941 | $0 | n/a |
LE0599 # 06 Y:2025 | 06 | 2025 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $98,974 | $65,000 | n/a |
LE0599 # 10 Y:2025 | 10 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,348 | $166,600 | n/a |
LE0599 # 02 Y:2025 | 02 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,295 | $100 | n/a |
LE0599 # 11 Y:2025 | 11 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $32,291 | $137,607 | n/a |
LE0599 # 08 Y:2025 | 08 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $808 | $1,500 | n/a |
LE0599 # 03 Y:2025 | 03 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,855 | $7,000 | n/a |
LE0599 # 01 Y:2025 | 01 | 2025 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,231 | $50 | n/a |
LE0599 # 04 Y:2025 | 04 | 2025 | UPGRADE OBSOLETE EQUIPMENT | $66,584 | $25,000 | n/a |
LE0599 # 09 Y:2025 | 09 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,397 | $22,164 | n/a |
LE0599 # 05 Y:2025 | 05 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,274 | $2,000 | n/a |
LE0599 # 12 Y:2025 | 12 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,690 | $12,500 | n/a |
LE0599 # 07 Y:2025 | 07 | 2025 | BURN A LESS EXPENSIVE GRADE OF FUEL | $2,581 | $4,000 | n/a |
MZ0373 # 03 Y:2025 | 03 | 2025 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $2,122 | $500 | n/a |
MZ0373 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,710 | $120 | n/a |
MZ0373 # 01 Y:2025 | 01 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,877 | $6,000 | n/a |