Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
189
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0133 # 06 Y:1988 | 06 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $744 | $200 | Implemented |
CO0133 # 07 Y:1988 | 07 | 1988 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $300 | $300 | Implemented |
CO0133 # 09 Y:1988 | 09 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,932 | $752 | Implemented |
CO0125 # 03 Y:1988 | 03 | 1988 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $806 | $250 | Implemented |
CO0125 # 04 Y:1988 | 04 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $415 | $288 | Implemented |
CO0110 # 01 Y:1987 | 01 | 1987 | INSULATE BARE EQUIPMENT | $4,100 | $6,900 | Implemented |
CO0110 # 02 Y:1987 | 02 | 1987 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $6,195 | $500 | Implemented |
CO0110 # 03 Y:1987 | 03 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $349 | $200 | Implemented |
CO0110 # 04 Y:1987 | 04 | 1987 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,030 | $250 | Implemented |
CO0110 # 06 Y:1987 | 06 | 1987 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,602 | $35 | Implemented |
CO0110 # 07 Y:1987 | 07 | 1987 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $264 | $150 | Implemented |
CO0110 # 08 Y:1987 | 08 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $610 | $424 | Implemented |
CO0097 # 01 Y:1987 | 01 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $156 | $100 | Implemented |
CO0097 # 03 Y:1987 | 03 | 1987 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $2,950 | $65 | Implemented |
CO0097 # 06 Y:1987 | 06 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $3,327 | $3,200 | Implemented |
CO0097 # 07 Y:1987 | 07 | 1987 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $290 | $690 | Implemented |
CO0097 # 08 Y:1987 | 08 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,483 | $577 | Implemented |
CO0053 # 01 Y:1986 | 01 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $1,025 | $1,200 | Implemented |
CO0053 # 03 Y:1986 | 03 | 1986 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,522 | $280 | Implemented |
CO0053 # 07 Y:1986 | 07 | 1986 | IMPROVE LUBRICATION PRACTICES | $1,616 | $0 | Implemented |
CO0053 # 09 Y:1986 | 09 | 1986 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $8,286 | $50,000 | Implemented |
CO0053 # 10 Y:1986 | 10 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,306 | $842 | Implemented |
CO0047 # 02 Y:1985 | 02 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $956 | $150 | Implemented |
CO0047 # 03 Y:1985 | 03 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $414 | $1,200 | Implemented |
CO0032 # 02 Y:1985 | 02 | 1985 | SEPARATE CONTROLS OF AIR HANDLERS FROM AC/ HEATING SYSTEMS | $816 | $2,000 | Implemented |