Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
204
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2409 # 03 Y:2024 | 03 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $264 | $0 | n/a |
UC2409 # 09 Y:2024 | 09 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,316 | $22,456 | n/a |
UC2409 # 10 Y:2024 | 10 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $97,545 | $403,849 | n/a |
UC2409 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,298 | $1,300 | n/a |
UC2409 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $813 | $75 | n/a |
UC2409 # 02 Y:2024 | 02 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $10,580 | $0 | n/a |
UC2409 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,347 | $15,260 | n/a |
UC2409 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $957 | $6,632 | n/a |
UC2409 # 08 Y:2024 | 08 | 2024 | REPLACE BOILER | $28,994 | $154,002 | n/a |
UC2409 # 01 Y:2024 | 01 | 2024 | PAY UTILITY BILLS ON TIME | $517 | $0 | n/a |
UC2402 # 08 Y:2024 | 08 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,934 | $155 | n/a |
UC2402 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $7,849 | $31,027 | n/a |
UC2402 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,943 | $1,040 | n/a |
UC2402 # 09 Y:2024 | 09 | 2024 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $6,701 | $64,088 | n/a |
UC2402 # 05 Y:2024 | 05 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,261 | $150 | n/a |
UC2402 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $17,049 | $134,289 | n/a |
UC2402 # 06 Y:2024 | 06 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,612 | $30 | n/a |
UC2402 # 03 Y:2024 | 03 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,298 | $3,327 | n/a |
UC2402 # 07 Y:2024 | 07 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $419 | $1,300 | n/a |
UC2305 # 12 Y:2023 | 12 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $17,010 | $126,560 | Not Implemented |
UC2305 # 08 Y:2023 | 08 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $173 | $30 | Not Implemented |
UC2305 # 02 Y:2023 | 02 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,483 | $0 | Implemented |
UC2305 # 09 Y:2023 | 09 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,885 | $28,876 | Implemented |
UC2305 # 10 Y:2023 | 10 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $25,926 | $115,275 | Not Implemented |
UC2305 # 03 Y:2023 | 03 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,923 | $0 | Implemented |