Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,163
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0211 # 06 Y:1994 | 06 | 1994 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $275 | $200 | Not Implemented |
KG0001 # 01 Y:1994 | 01 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,187 | $0 | Implemented |
KG0001 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $8,319 | $129 | Not Implemented |
KG0001 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,000 | $8,050 | Not Implemented |
KG0001 # 04 Y:1994 | 04 | 1994 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $2,284 | $22,000 | Not Implemented |
KG0001 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $795 | $238 | Not Implemented |
KG0001 # 06 Y:1994 | 06 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $580 | $310 | Not Implemented |
AM0188 # 01 Y:1993 | 01 | 1993 | INCREASE AMOUNT OF CONDENSATE RETURNED | $3,000 | $10,580 | Not Implemented |
AM0188 # 02 Y:1993 | 02 | 1993 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,390 | $2,890 | Implemented |
AM0188 # 03 Y:1993 | 03 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $2,360 | $1,040 | Implemented |
AM0188 # 04 Y:1993 | 04 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,500 | $400 | Implemented |
AM0188 # 05 Y:1993 | 05 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $595 | $1,790 | Implemented |
AM0188 # 06 Y:1993 | 06 | 1993 | INSTALL SKYLIGHTS | $310 | $375 | Not Implemented |
AM0183 # 01 Y:1993 | 01 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,600 | $900 | Implemented |
AM0183 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,260 | $1,570 | Implemented |
AM0183 # 03 Y:1993 | 03 | 1993 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,640 | $6,410 | Not Implemented |
AM0183 # 04 Y:1993 | 04 | 1993 | OPTIMIZE PLANT POWER FACTOR | $3,000 | $9,000 | Not Implemented |
AM0183 # 05 Y:1993 | 05 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $145 | $820 | Implemented |
AM0153 # 01 Y:1992 | 01 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,980 | $420 | Implemented |
AM0153 # 02 Y:1992 | 02 | 1992 | PAY UTILITY BILLS ON TIME | $1,768 | $0 | Implemented |
AM0153 # 03 Y:1992 | 03 | 1992 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,230 | $3,386 | Implemented |
AM0153 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,929 | $0 | Implemented |
AM0153 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $746 | $640 | Implemented |
AM0153 # 06 Y:1992 | 06 | 1992 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $215 | $215 | Not Implemented |
AM0153 # 07 Y:1992 | 07 | 1992 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $160 | $360 | Not Implemented |