Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,026
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NV0031 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,350 | $3,190 | Implemented |
NV0031 # 02 Y:1995 | 02 | 1995 | INSTALL OCCUPANCY SENSORS | $433 | $327 | Not Implemented |
NV0031 # 03 Y:1995 | 03 | 1995 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,745 | $5,526 | Not Implemented |
NV0031 # 04 Y:1995 | 04 | 1995 | UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS | $875 | $888 | Not Implemented |
NV0031 # 05 Y:1995 | 05 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,424 | $3,622 | Implemented |
NV0031 # 06 Y:1995 | 06 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,798 | $0 | Implemented |
NV0031 # 07 Y:1995 | 07 | 1995 | INSULATE BARE EQUIPMENT | $3,364 | $1,444 | Not Implemented |
NV0031 # 08 Y:1995 | 08 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,776 | $0 | Implemented |
NV0031 # 09 Y:1995 | 09 | 1995 | OPTIMIZE PLANT POWER FACTOR | $982 | $3,382 | Implemented |
KG0025 # 01 Y:1995 | 01 | 1995 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $28,787 | $7,200 | Implemented |
KG0025 # 02 Y:1995 | 02 | 1995 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $21,682 | $0 | Not Implemented |
KG0025 # 03 Y:1995 | 03 | 1995 | INSULATE BARE EQUIPMENT | $20,807 | $284 | Implemented |
KG0025 # 04 Y:1995 | 04 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,160 | $6,450 | Implemented |
KG0025 # 05 Y:1995 | 05 | 1995 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $2,950 | $60 | Not Implemented |
KG0025 # 06 Y:1995 | 06 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,632 | $20 | Implemented |
KG0025 # 07 Y:1995 | 07 | 1995 | INSTALL OCCUPANCY SENSORS | $451 | $325 | Implemented |
MA0342 # 01 Y:1995 | 01 | 1995 | OPTIMIZE PLANT POWER FACTOR | $10,527 | $8,100 | Implemented |
MA0342 # 02 Y:1995 | 02 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,510 | $0 | Not Implemented |
MA0342 # 03 Y:1995 | 03 | 1995 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $5,090 | $25,000 | Not Implemented |
MA0342 # 04 Y:1995 | 04 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,836 | $0 | Implemented |
MA0342 # 05 Y:1995 | 05 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,525 | $3,443 | Implemented |
MA0342 # 06 Y:1995 | 06 | 1995 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,705 | $7,770 | Not Implemented |
MA0342 # 07 Y:1995 | 07 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,776 | $725 | Not Implemented |
MA0342 # 08 Y:1995 | 08 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $797 | $0 | Implemented |
MA0342 # 09 Y:1995 | 09 | 1995 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $547 | $1,500 | Not Implemented |