IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

290

matching recommendations
Reset
SIC 30 Rubber And Miscellaneous Plastics Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0085 # 06 Y:1990 06 1990 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $2,647 $7,200 Not Implemented
AS0005 # 01 Y:1990 01 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,187 $250 Not Implemented
AS0005 # 02 Y:1990 02 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,723 $310 Not Implemented
AS0005 # 03 Y:1990 03 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $550 $729 Not Implemented
MA0180 # 01 Y:1990 01 1990 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $7,523 $5,750 Implemented
MA0180 # 02 Y:1990 02 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,604 $334 Implemented
MA0180 # 03 Y:1990 03 1990 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $5,957 $6,200 Not Implemented
UD0319 # 01 Y:1990 01 1990 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $10,147 $0 Implemented
UD0319 # 02 Y:1990 02 1990 USE DEMAND CONTROLLER OR LOAD SHEDDER $1,320 $0 Implemented
UD0319 # 03 Y:1990 03 1990 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $13,053 $0 Implemented
UD0319 # 04 Y:1990 04 1990 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $20,790 $0 Implemented
RU0089 # 01 Y:1990 01 1990 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,307 $500 Implemented
RU0089 # 02 Y:1990 02 1990 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $339 $75 Not Implemented
RU0089 # 03 Y:1990 03 1990 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $16,780 $5,000 Implemented
RU0089 # 04 Y:1990 04 1990 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,389 $2,520 Implemented
RU0089 # 05 Y:1990 05 1990 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $931 $68 Not Implemented
RU0089 # 06 Y:1990 06 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $521 $300 Implemented
MA0179 # 01 Y:1990 01 1990 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $13,039 $43,000 Not Implemented
MA0179 # 02 Y:1990 02 1990 RECOVER AND REUSE COOLING WATER $10,670 $8,250 Implemented
MA0179 # 03 Y:1990 03 1990 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $11,908 $2,350 Not Implemented
MA0179 # 04 Y:1990 04 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $554 $70 Implemented
UD0316 # 01 Y:1990 01 1990 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $12,000 $0 Not Implemented
UD0316 # 02 Y:1990 02 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,890 $0 Not Implemented
UD0316 # 03 Y:1990 03 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,175 $0 Not Implemented
UD0316 # 04 Y:1990 04 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $6,611 $0 Not Implemented