Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1990 |
Principal Product | PLASTIC BOTTLES |
NAICS | n/a |
SIC | 3085 - Plastics Bottles |
Sales | $5,000,000-$10,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 45,000,000 Pieces |
Production Hrs. Annual | 8,736 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $180,580 | 7,155,920 | kWh | $0.03 |
TOTAL ENERGY COSTS | $180,580 | |||
RECOMMENDED SAVINGS* | $121,601 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $117,818 |
#|Description |
Savings Cost |
Status | Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.5314 USE IN-PROCESS RECYCLING WHENEVER POSSIBLE |
Savings: $112,370 Cost: $38,400 |
$(-8,336) | (-255,276) | $120,706 | - |
$(-8,336) (-255,276) kWh |
$120,706 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,965 Cost: $2,806 |
$1,463 | 62,134 | $3,502 | - |
$1,463 62,134 kWh |
$3,502 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $389 Cost: $240 |
$389 | 13,482 | - | - |
$389 13,482 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $483 Cost: $909 |
$483 | 18,464 | - | - |
$483 18,464 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $747 Cost: $1,385 |
$747 | 40,445 | - | - |
$747 40,445 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $2,647 Cost: $7,200 |
$2,647 | 143,025 | - | - |
$2,647 143,025 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $121,601 Cost: $50,940 |
$(-2,607) | 22,274 | $124,208 | - | $(-2,607) 22,274 kWh |
$124,208 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $117,818 Cost: $42,115 |
$(-6,390) | (-174,678) | $124,208 | - | $(-6,390) (-174,678) kWh |
$124,208 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes |