IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

32

matching recommendations
Reset
SIC 301 Tires And Inner Tubes
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TT0214 # 01 Y:2019 01 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $223,429 $3,000 Implemented
TT0214 # 06 Y:2019 06 2019 OPTIMIZE PLANT POWER FACTOR $13,401 $5,000 Implemented
TT0214 # 04 Y:2019 04 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $24,330 $66,000 Not Implemented
TT0214 # 07 Y:2019 07 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,443 $15,674 Not Implemented
TT0214 # 03 Y:2019 03 2019 REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT $24,664 $106,000 Not Implemented
TT0214 # 02 Y:2019 02 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $64,974 $152,490 Not Implemented
TT0214 # 05 Y:2019 05 2019 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $23,715 $75,000 Not Implemented
TT0132 # 03 Y:2014 03 2014 OPTIMIZE PLANT POWER FACTOR $21,103 $6,000 Not Implemented
TT0132 # 14 Y:2014 14 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $892 $850 Not Implemented
TT0132 # 13 Y:2014 13 2014 DISCONNECT BALLASTS $1,153 $63 Not Implemented
TT0132 # 12 Y:2014 12 2014 REDUCE FLUID FLOW RATES $893 $1,000 Not Implemented
TT0132 # 11 Y:2014 11 2014 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,407 $8,750 Implemented
TT0132 # 10 Y:2014 10 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $485 $50 Not Implemented
TT0132 # 09 Y:2014 09 2014 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $37,546 $80,000 Not Implemented
TT0132 # 08 Y:2014 08 2014 INSTALL COMMON HEADER ON COMPRESSORS $3,556 $12,000 Not Implemented
TT0132 # 07 Y:2014 07 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,145 $7,000 Not Implemented
TT0132 # 06 Y:2014 06 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,643 $0 Not Implemented
TT0132 # 05 Y:2014 05 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $894 $1,750 Not Implemented
TT0132 # 04 Y:2014 04 2014 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $13,713 $25,000 Implemented
TT0132 # 02 Y:2014 02 2014 INSTALL / REPAIR INSULATION ON STEAM LINES $13,762 $17,000 Not Implemented
TT0132 # 01 Y:2014 01 2014 INSTALL / REPAIR INSULATION ON STEAM LINES $12,064 $20,731 Implemented
TN0648 # 08 Y:1999 08 1999 REUSE / RECYCLE/ SELL RUBBER PRODUCTS $39,770 $104,630 Not Implemented
TN0648 # 06 Y:1999 06 1999 IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) $8,510 $16,470 Not Implemented
TN0648 # 05 Y:1999 05 1999 INSULATE BARE EQUIPMENT $12,600 $6,880 Not Implemented
TN0648 # 03 Y:1999 03 1999 INCREASE USE OF AUTOMATION $32,400 $5,020 Not Implemented