Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
411
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1085 # 05 Y:2023 | 05 | 2023 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $564 | $0 | Implemented |
OK1085 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,322 | $2,730 | Implemented |
OK1085 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $72,249 | $820,666 | Not Implemented |
OK1085 # 04 Y:2023 | 04 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $15,984 | $2,567 | Implemented |
OK1085 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,853 | $0 | Implemented |
OK1065 # 01 Y:2022 | 01 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,073 | $12,233 | Implemented |
OK1065 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,433 | $2,429 | Implemented |
OK1065 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $29,263 | $0 | Implemented |
OK1065 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,273 | $21,539 | Implemented |
OK1057 # 03 Y:2021 | 03 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $533 | $1,400 | Not Implemented |
OK1057 # 02 Y:2021 | 02 | 2021 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $12,483 | $56,000 | Implemented |
OK1057 # 01 Y:2021 | 01 | 2021 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $10,601 | $1,701 | Implemented |
OK1057 # 04 Y:2021 | 04 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,960 | $0 | Implemented |
OK1017 # 02 Y:2019 | 02 | 2019 | INSTALL / REPAIR INSULATION ON STEAM LINES | $10,627 | $231 | Not Implemented |
OK1017 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,214 | $3,590 | Not Implemented |
OK1017 # 05 Y:2019 | 05 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,164 | $0 | Not Implemented |
OK1017 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,220 | $22,288 | Not Implemented |
OK1017 # 01 Y:2019 | 01 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,604 | $17,500 | Not Implemented |
OK0992 # 06 Y:2018 | 06 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,701 | $15,796 | Implemented |
OK0992 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $604 | $450 | Implemented |
OK0992 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $308 | $259 | Implemented |
OK0992 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $171 | $1,243 | Not Implemented |
OK0992 # 08 Y:2018 | 08 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $360 | $45 | Not Implemented |
OK0992 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $208 | $0 | Implemented |
OK0992 # 09 Y:2018 | 09 | 2018 | PAY UTILITY BILLS ON TIME | $310 | $0 | Implemented |