IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

896

matching recommendations
Reset
SIC 308 Miscellaneous Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0228 # 03 Y:1995 03 1995 INSTALL SKYLIGHTS $630 $1,140 Not Implemented
AM0228 # 04 Y:1995 04 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,119 $242 Implemented
KG0015 # 01 Y:1994 01 1994 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,992 $0 Implemented
KG0015 # 02 Y:1994 02 1994 INSULATE BARE EQUIPMENT $3,720 $118 Not Implemented
KG0015 # 03 Y:1994 03 1994 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,824 $2,390 Not Implemented
KG0015 # 04 Y:1994 04 1994 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT $1,458 $2,300 Not Implemented
KG0015 # 05 Y:1994 05 1994 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $799 $15 Implemented
KG0015 # 06 Y:1994 06 1994 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $407 $162 Implemented
AM0220 # 01 Y:1994 01 1994 OPTIMIZE PLANT POWER FACTOR $96,105 $145,000 Implemented
AM0220 # 02 Y:1994 02 1994 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $44,845 $120,000 Implemented
AM0220 # 03 Y:1994 03 1994 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $37,861 $92,046 Implemented
AM0220 # 04 Y:1994 04 1994 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $26,620 $3,800 Implemented
AM0220 # 05 Y:1994 05 1994 INSTALL OCCUPANCY SENSORS $12,915 $6,250 Implemented
AM0220 # 06 Y:1994 06 1994 WASH AND REUSE RAGS ON-SITE $2,070 $7,900 Implemented
AM0220 # 07 Y:1994 07 1994 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES $670 $2,400 Implemented
KG0001 # 01 Y:1994 01 1994 TURN OFF EQUIPMENT WHEN NOT IN USE $9,187 $0 Implemented
KG0001 # 02 Y:1994 02 1994 INSULATE BARE EQUIPMENT $8,319 $129 Not Implemented
KG0001 # 03 Y:1994 03 1994 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $7,000 $8,050 Not Implemented
KG0001 # 04 Y:1994 04 1994 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $2,284 $22,000 Not Implemented
KG0001 # 05 Y:1994 05 1994 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $795 $238 Not Implemented
KG0001 # 06 Y:1994 06 1994 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $580 $310 Not Implemented
AM0153 # 01 Y:1992 01 1992 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,980 $420 Implemented
AM0153 # 02 Y:1992 02 1992 PAY UTILITY BILLS ON TIME $1,768 $0 Implemented
AM0153 # 03 Y:1992 03 1992 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $1,230 $3,386 Implemented
AM0153 # 04 Y:1992 04 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,929 $0 Implemented