Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
13,403
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0015 # 03 Y:1985 | 03 | 1985 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $36,316 | $15,000 | Not Implemented |
MA0015 # 04 Y:1985 | 04 | 1985 | AIR CONDITION ONLY SPACE NECESSARY | $1,416 | $4,000 | Not Implemented |
OK0156 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $567 | $161 | Not Implemented |
OK0156 # 02 Y:1985 | 02 | 1985 | OPTIMIZE PLANT POWER FACTOR | $5,639 | $7,640 | Implemented |
OK0156 # 03 Y:1985 | 03 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,728 | $14,629 | Not Implemented |
OK0156 # 04 Y:1985 | 04 | 1985 | RECOVER AND REUSE COOLING WATER | $1,387 | $500 | Implemented |
OK0156 # 05 Y:1985 | 05 | 1985 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,307 | $624 | Implemented |
OK0156 # 06 Y:1985 | 06 | 1985 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $9,735 | $0 | Not Implemented |
OK0156 # 07 Y:1985 | 07 | 1985 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,633 | $531 | Not Implemented |
OK0156 # 08 Y:1985 | 08 | 1985 | INSULATE BARE EQUIPMENT | $300 | $329 | Not Implemented |
OK0156 # 09 Y:1985 | 09 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $1,230 | $300 | Not Implemented |
OK0156 # 10 Y:1985 | 10 | 1985 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,411 | $0 | Implemented |
OK0156 # 11 Y:1985 | 11 | 1985 | INSULATE BARE EQUIPMENT | $290 | $880 | Implemented |
OK0156 # 12 Y:1985 | 12 | 1985 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $11,431 | $0 | Not Implemented |
KU0150 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,190 | $3,365 | Not Implemented |
KU0150 # 02 Y:1985 | 02 | 1985 | INSULATE BARE EQUIPMENT | $993 | $1,300 | Not Implemented |
KU0150 # 03 Y:1985 | 03 | 1985 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $567 | $0 | Not Implemented |
KU0150 # 04 Y:1985 | 04 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $749 | $200 | Implemented |
KU0150 # 05 Y:1985 | 05 | 1985 | USE COMPRESSOR AIR FILTERS | $214 | $0 | Implemented |
KU0150 # 06 Y:1985 | 06 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $935 | $0 | Not Implemented |
KU0150 # 07 Y:1985 | 07 | 1985 | INSTALL AUTOMATIC STACK DAMPER | $761 | $400 | Not Implemented |
KU0150 # 08 Y:1985 | 08 | 1985 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $284 | $100 | Implemented |
KU0150 # 09 Y:1985 | 09 | 1985 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,016 | $131 | Implemented |
KU0150 # 10 Y:1985 | 10 | 1985 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $835 | $1,500 | Not Implemented |
KU0150 # 11 Y:1985 | 11 | 1985 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $719 | $265 | Implemented |