Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
298
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
HO0068 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,494 | $1,956 | Not Implemented |
HO0068 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $786 | $1,283 | Implemented |
HO0068 # 04 Y:1994 | 04 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,378 | $1,000 | Not Implemented |
HO0068 # 05 Y:1994 | 05 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $174 | $600 | Implemented |
HO0068 # 06 Y:1994 | 06 | 1994 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $8,520 | $2,500 | Not Implemented |
HO0068 # 07 Y:1994 | 07 | 1994 | USE SYNTHETIC LUBRICANT | $1,222 | $0 | Not Implemented |
RU0163 # 01 Y:1992 | 01 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,527 | $5,750 | Not Implemented |
RU0163 # 02 Y:1992 | 02 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $11,072 | $1,266 | Not Implemented |
RU0163 # 03 Y:1992 | 03 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,852 | $0 | Implemented |
RU0163 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,576 | $196 | Not Implemented |
RU0138 # 01 Y:1992 | 01 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,857 | $0 | Implemented |
RU0138 # 02 Y:1992 | 02 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $591 | $40 | Implemented |
RU0138 # 03 Y:1992 | 03 | 1992 | IMPROVE LUBRICATION PRACTICES | $1,884 | $800 | Not Implemented |
RU0138 # 04 Y:1992 | 04 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $803 | $36,020 | Implemented |
RU0138 # 05 Y:1992 | 05 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,600 | $2,500 | Not Implemented |
RU0131 # 01 Y:1991 | 01 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,853 | $0 | Not Implemented |
RU0131 # 02 Y:1991 | 02 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $17,417 | $46,695 | Not Implemented |
RU0131 # 03 Y:1991 | 03 | 1991 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $18,330 | $0 | Not Implemented |
RU0128 # 01 Y:1991 | 01 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,552 | $0 | Implemented |
RU0128 # 02 Y:1991 | 02 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $554 | $42 | Implemented |
RU0128 # 03 Y:1991 | 03 | 1991 | IMPROVE LUBRICATION PRACTICES | $1,753 | $800 | Implemented |
RU0128 # 04 Y:1991 | 04 | 1991 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $2,320 | $0 | Implemented |
RU0128 # 05 Y:1991 | 05 | 1991 | INSULATE BARE EQUIPMENT | $630 | $169 | Implemented |
RU0128 # 06 Y:1991 | 06 | 1991 | USE OPTIMUM TEMPERATURE | $4,975 | $6,700 | Implemented |
RU0117 # 01 Y:1991 | 01 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,153 | $0 | Implemented |