Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
87
matching recommendationsSIC | 3084 | Plastics Pipe |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1065 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,273 | $21,539 | Implemented |
OK1065 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,433 | $2,429 | Implemented |
OK1065 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $29,263 | $0 | Implemented |
OK1065 # 01 Y:2022 | 01 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,073 | $12,233 | Implemented |
OK1057 # 04 Y:2021 | 04 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,960 | $0 | Implemented |
OK1057 # 03 Y:2021 | 03 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $533 | $1,400 | Not Implemented |
OK1057 # 02 Y:2021 | 02 | 2021 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $12,483 | $56,000 | Implemented |
OK1057 # 01 Y:2021 | 01 | 2021 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $10,601 | $1,701 | Implemented |
OK0947 # 07 Y:2016 | 07 | 2016 | OPTIMIZE PLANT POWER FACTOR | $4,680 | $27,500 | Not Implemented |
OK0947 # 01 Y:2016 | 01 | 2016 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $11,871 | $92,000 | Not Implemented |
OK0947 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $985 | $3,780 | Not Implemented |
OK0947 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,495 | $9,720 | Not Implemented |
OK0947 # 04 Y:2016 | 04 | 2016 | INSULATE BARE EQUIPMENT | $11,683 | $10,036 | Not Implemented |
OK0947 # 05 Y:2016 | 05 | 2016 | USE RADIANT HEATER FOR SPOT HEATING | $3,754 | $19,570 | Not Implemented |
OK0947 # 06 Y:2016 | 06 | 2016 | INSTALL SET-BACK TIMERS | $483 | $410 | Not Implemented |
OK0947 # 08 Y:2016 | 08 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $368 | $822 | Not Implemented |
OK0947 # 09 Y:2016 | 09 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,092 | $2,000 | Not Implemented |
OK0947 # 10 Y:2016 | 10 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $362 | $540 | Not Implemented |
OK0916 # 08 Y:2015 | 08 | 2015 | OPTIMIZE PLANT POWER FACTOR | $3,788 | $26,134 | Not Implemented |
OK0916 # 01 Y:2015 | 01 | 2015 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $12,740 | $0 | Implemented |
OK0916 # 02 Y:2015 | 02 | 2015 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $16,433 | $20,074 | Not Implemented |
OK0916 # 03 Y:2015 | 03 | 2015 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $30,382 | $0 | Implemented |
OK0916 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,579 | $3,451 | Implemented |
OK0916 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $390 | $1,805 | Not Implemented |
OK0916 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,606 | $5,687 | Not Implemented |