IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

8

matching recommendations
Reset
SIC 3229 Pressed And Blown Glass, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NC0556 # 01 Y:2015 01 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $59,808 $90,000 Implemented
NC0556 # 02 Y:2015 02 2015 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,806 $5,000 Not Implemented
NC0556 # 03 Y:2015 03 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,438 $12,000 Implemented
NC0556 # 04 Y:2015 04 2015 RECOVER WASTE HEAT FROM EQUIPMENT $9,076 $3,200 Not Implemented
NC0556 # 05 Y:2015 05 2015 DEVELOP A REPAIR/REPLACE POLICY $1,836 $4,256 Implemented
NC0556 # 06 Y:2015 06 2015 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,228 $200 Not Implemented
NC0556 # 07 Y:2015 07 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,584 $8,350 Implemented
NC0556 # 08 Y:2015 08 2015 INSTALL OCCUPANCY SENSORS $578 $868 Implemented