Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,548
matching recommendationsSIC | 327 | Concrete, Gypsum, And Plaster Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0570 # 01 Y:2024 | 01 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $9,292 | $0 | Implemented |
LE0570 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $55,246 | $42,000 | Implemented |
LE0570 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $25,168 | $26,500 | Implemented |
LE0570 # 05 Y:2024 | 05 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,252 | $5,000 | Implemented |
LE0570 # 06 Y:2024 | 06 | 2024 | INSTALL BACK-UP EQUIPMENT | $46,731 | $90,000 | Implemented |
UW2404 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $34,140 | $25,000 | Implemented |
UW2404 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $28,693 | $75,000 | Implemented |
UW2404 # 05 Y:2024 | 05 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $15,990 | $112,500 | Implemented |
UW2404 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $114,442 | $742,868 | Not Implemented |
UW2404 # 01 Y:2024 | 01 | 2024 | OPTIMIZE PLANT POWER FACTOR | $141,402 | $150,381 | Implemented |
DL0234 # 03 Y:2024 | 03 | 2024 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $95,717 | $35,600 | Not Implemented |
DL0234 # 02 Y:2024 | 02 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $21,550 | $30,000 | Not Implemented |
DL0234 # 01 Y:2024 | 01 | 2024 | ISOLATE HOT OR COLD EQUIPMENT | $36,400 | $82,500 | Not Implemented |
DL0234 # 04 Y:2024 | 04 | 2024 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $76,734 | $166,100 | Not Implemented |
DL0231 # 08 Y:2024 | 08 | 2024 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $266,000 | $385,800 | Not Implemented |
DL0231 # 07 Y:2024 | 07 | 2024 | IMPROVE COMBUSTION CONTROL CAPABILITY | $211,766 | $21,800 | Not Implemented |
DL0231 # 06 Y:2024 | 06 | 2024 | MAINTAIN MACHINES TO REDUCE LEAKS | $441,845 | $39,600 | Not Implemented |
DL0231 # 04 Y:2024 | 04 | 2024 | INSULATE BARE EQUIPMENT | $25,112 | $9,768 | Not Implemented |
DL0231 # 05 Y:2024 | 05 | 2024 | MAINTAIN MACHINES TO REDUCE LEAKS | $132,876 | $34,600 | Not Implemented |
DL0231 # 02 Y:2024 | 02 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $229,694 | $2,880,000 | Not Implemented |
DL0231 # 03 Y:2024 | 03 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $149,450 | $333,800 | Not Implemented |
DL0231 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $172,461 | $34,600 | Not Implemented |
UW2317 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $533 | $0 | Implemented |
UW2317 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $156 | $1,901 | Implemented |
UW2317 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $658 | $1,096 | Implemented |