IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

28

matching recommendations
Reset
SIC 3291 Abrasive Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UF0254 # 10 Y:2000 10 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $65,000 $12,000 Not Implemented
UF0254 # 09 Y:2000 09 2000 INSTALL SENSORS TO DETECT DEFECTS $53,501 $5,465 Not Implemented
UF0254 # 08 Y:2000 08 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $32,500 $22,020 Not Implemented
UF0254 # 07 Y:2000 07 2000 RECOVER AND REUSE WASTE MATERIAL $73,125 $100,000 Not Implemented
UF0254 # 06 Y:2000 06 2000 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $7,529 $50 Implemented
UF0254 # 05 Y:2000 05 2000 DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING $1,420 $1,212 Implemented
UF0254 # 04 Y:2000 04 2000 INSULATE BARE EQUIPMENT $8,849 $2,975 Implemented
UF0254 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,374 $3,223 Implemented
UF0254 # 02 Y:2000 02 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $140,156 $26,813 Implemented
UF0254 # 01 Y:2000 01 2000 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $288,146 $1,200,000 Not Implemented
ND0353 # 02 Y:2000 02 2000 INSTALL OCCUPANCY SENSORS $573 $600 Not Implemented
ND0353 # 10 Y:2000 10 2000 METER WASTE WATER $1,127 $200 Implemented
ND0353 # 01 Y:2000 01 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,237 $10,801 Implemented
ND0353 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,205 $11,337 Implemented
ND0353 # 04 Y:2000 04 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,489 $300 Implemented
ND0353 # 05 Y:2000 05 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,107 $140 Implemented
ND0353 # 06 Y:2000 06 2000 DEVELOP A REPAIR/REPLACE POLICY $1,117 $1,714 Implemented
ND0353 # 07 Y:2000 07 2000 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $4,286 $8,120 Not Implemented
ND0353 # 08 Y:2000 08 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $20,782 $25,000 Implemented
ND0353 # 09 Y:2000 09 2000 MINIMIZE WATER USAGE $1,028 $4,025 Not Implemented
ND0353 # 11 Y:2000 11 2000 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $267 $200 Implemented
WI0365 # 01 Y:2000 01 2000 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $302,692 $770,000 Not Implemented
WI0365 # 02 Y:2000 02 2000 INSTALL SENSORS TO DETECT DEFECTS $100,000 $70,000 Not Implemented
WI0365 # 03 Y:2000 03 2000 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $8,830 $26,500 Implemented
WI0365 # 04 Y:2000 04 2000 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $9,131 $5,808 Implemented