IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,064

matching recommendations
Reset
SIC 331 Blast Furnace And Basic Steel Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TN0386 # 03 Y:1989 03 1989 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $3,664 $0 Implemented
TN0386 # 04 Y:1989 04 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,407 $3,860 Implemented
TN0386 # 05 Y:1989 05 1989 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,143 $0 Not Implemented
TN0386 # 06 Y:1989 06 1989 USE OPTIMUM THICKNESS INSULATION $851 $735 Not Implemented
TN0386 # 07 Y:1989 07 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $659 $500 Implemented
OK0274 # 01 Y:1989 01 1989 INSTALL TIMERS AND/OR THERMOSTATS $544 $350 Implemented
OK0274 # 02 Y:1989 02 1989 INSULATE BARE EQUIPMENT $6,510 $1,958 Not Implemented
OK0274 # 03 Y:1989 03 1989 INSULATE BARE EQUIPMENT $23,241 $3,556 Implemented
OK0274 # 04 Y:1989 04 1989 COVER OPEN TANKS $11,365 $1,986 Not Implemented
OK0274 # 05 Y:1989 05 1989 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $18,511 $15,480 Not Implemented
OK0274 # 06 Y:1989 06 1989 UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS $2,113 $1,925 Implemented
OK0274 # 07 Y:1989 07 1989 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $5,496 $6,200 Not Implemented
RU0042 # 01 Y:1988 01 1988 IMPROVE LUBRICATION PRACTICES $11,892 $800 Not Implemented
RU0042 # 02 Y:1988 02 1988 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $16,798 $21,400 Not Implemented
RU0042 # 03 Y:1988 03 1988 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $707 $302 Not Implemented
RU0042 # 04 Y:1988 04 1988 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,960 $0 Implemented
RU0042 # 05 Y:1988 05 1988 COVER OPEN TANKS $2,347 $400 Not Implemented
RU0042 # 06 Y:1988 06 1988 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,295 $1,510 Implemented
RU0042 # 07 Y:1988 07 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $35,736 $44,360 Implemented
RU0042 # 08 Y:1988 08 1988 TURN OFF EQUIPMENT WHEN NOT IN USE $29,075 $94,000 Implemented
OR0037 # 01 Y:1988 01 1988 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,463 $0 Not Implemented
OR0037 # 02 Y:1988 02 1988 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $14,466 $300 Not Implemented
OR0037 # 03 Y:1988 03 1988 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,754 $500 Implemented
OR0037 # 04 Y:1988 04 1988 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $37,296 $10,000 Implemented
OR0037 # 05 Y:1988 05 1988 INSULATE BARE EQUIPMENT $1,893 $2,025 Not Implemented