IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

8

matching recommendations
Reset
SIC 3317 Steel Pipe And Tubes
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0425 # 01 Y:2003 01 2003 RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION $1,157,000 $0 Not Implemented
AM0425 # 02 Y:2003 02 2003 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $243,880 $16,000 Implemented
AM0425 # 03 Y:2003 03 2003 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $154,000 $2,000 Implemented
AM0425 # 04 Y:2003 04 2003 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE $110,500 $0 Implemented
AM0425 # 05 Y:2003 05 2003 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $42,200 $700 Implemented
AM0425 # 06 Y:2003 06 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $29,700 $650 Implemented
AM0425 # 07 Y:2003 07 2003 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $13,500 $16,800 Implemented
AM0425 # 08 Y:2003 08 2003 PAY BILLS ON TIME TO AVOID LATE FEES $2,006 $0 Implemented