Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
122
matching recommendationsSIC | 336 | Nonferrous Foundries (castings) |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0402 # 08 Y:2012 | 08 | 2012 | USE FLUE GASES IN RADIANT HEATER FOR SPACE HEATING, OVENS, ETC | $11,060 | $15,000 | Not Implemented |
UM0402 # 07 Y:2012 | 07 | 2012 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $52,867 | $2,000 | Not Implemented |
UM0402 # 06 Y:2012 | 06 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $19,391 | $4,000 | Not Implemented |
UM0402 # 05 Y:2012 | 05 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,676 | $4,000 | Not Implemented |
UM0402 # 04 Y:2012 | 04 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,600 | $2,000 | Not Implemented |
UM0402 # 03 Y:2012 | 03 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,496 | $2,000 | Implemented |
UM0402 # 02 Y:2012 | 02 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,300 | $200 | Implemented |
UM0402 # 01 Y:2012 | 01 | 2012 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $6,681 | $200 | Implemented |
UMS004 # 01 Y:2012 | 01 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $200,000 | $200,000 | Not Implemented |
UMS004 # 02 Y:2012 | 02 | 2012 | CONVERT TO OXYFUEL BURNERS | $156,000 | $250,000 | Not Implemented |
UMS004 # 07 Y:2012 | 07 | 2012 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $1,300 | $0 | Not Implemented |
UMS004 # 06 Y:2012 | 06 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $40,000 | $40,000 | Not Implemented |
UMS004 # 05 Y:2012 | 05 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,500 | $0 | Not Implemented |
UMS004 # 03 Y:2012 | 03 | 2012 | COVER OPEN TANKS | $41,000 | $32,000 | Not Implemented |
UMS004 # 04 Y:2012 | 04 | 2012 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $27,600 | $75,000 | Not Implemented |
UM0336 # 01 Y:2008 | 01 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $31,330 | $1,650 | Implemented |
UM0336 # 06 Y:2008 | 06 | 2008 | INSTALL OCCUPANCY SENSORS | $6,297 | $1,600 | Implemented |
UM0336 # 09 Y:2008 | 09 | 2008 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $93 | $93 | Not Implemented |
UM0336 # 08 Y:2008 | 08 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,766 | $260 | Not Implemented |
UM0336 # 04 Y:2008 | 04 | 2008 | REDUCE VENTILATION AIR | $8,256 | $2,001 | Not Implemented |
UM0336 # 07 Y:2008 | 07 | 2008 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,932 | $1,000 | Implemented |
UM0336 # 03 Y:2008 | 03 | 2008 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $13,866 | $29,119 | Not Implemented |
UM0336 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,116 | $200 | Implemented |
UM0336 # 05 Y:2008 | 05 | 2008 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,239 | $10,900 | Not Implemented |
UM0235 # 03 Y:2003 | 03 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,576 | $9,600 | Implemented |