Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,274
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0607 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,524 | $11,610 | Implemented |
SF0607 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $41,060 | $346,427 | Implemented |
UC2310 # 08 Y:2023 | 08 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,756 | $225 | Implemented |
UC2310 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,607 | $1,900 | Implemented |
UC2310 # 06 Y:2023 | 06 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,547 | $1,283 | Implemented |
UC2310 # 05 Y:2023 | 05 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $6,045 | $40,103 | Implemented |
UC2310 # 03 Y:2023 | 03 | 2023 | PAY UTILITY BILLS ON TIME | $146 | $0 | Implemented |
UC2310 # 02 Y:2023 | 02 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,116 | $0 | Implemented |
UC2310 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,838 | $0 | Implemented |
UC2310 # 09 Y:2023 | 09 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,865 | $5,326 | Implemented |
UC2310 # 10 Y:2023 | 10 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,459 | $150 | Implemented |
UC2310 # 11 Y:2023 | 11 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,068 | $75 | Implemented |
AM0887 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $912 | $1,783 | Implemented |
AM0887 # 05 Y:2023 | 05 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,340 | $850 | Implemented |
AM0887 # 04 Y:2023 | 04 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,360 | $303 | Implemented |
AM0887 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,830 | $1,000 | Implemented |
MS0417 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,886 | $2,761 | Implemented |
NL0081 # 01 Y:2023 | 01 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $497,815 | $199,200 | Implemented |
NL0081 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $15,605 | $20,000 | Implemented |
NL0081 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,819 | $5,000 | Implemented |
NT0015 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,401 | $0 | Implemented |
NT0015 # 05 Y:2023 | 05 | 2023 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $349 | $0 | Implemented |
NT0015 # 03 Y:2023 | 03 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,242 | $1,258 | Implemented |
NT0015 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,648 | $5,609 | Implemented |
MU0030 # 12 Y:2023 | 12 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,604 | $0 | Implemented |