Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
525
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0548 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $87,415 | $1,061,947 | Implemented |
AS0548 # 02 Y:2023 | 02 | 2023 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $9,740 | $208 | Implemented |
AS0548 # 04 Y:2023 | 04 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $3,626 | $9,286 | Implemented |
AS0548 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,351 | $1,947 | Implemented |
AS0548 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,109 | $5,233 | Implemented |
AS0510 # 01 Y:2021 | 01 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $18,281 | $200 | Not Implemented |
AS0510 # 08 Y:2021 | 08 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $690 | $40 | Not Implemented |
AS0510 # 07 Y:2021 | 07 | 2021 | UPGRADE CONTROLS ON COMPRESSORS | $713 | $3,359 | Implemented |
AS0510 # 06 Y:2021 | 06 | 2021 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,097 | $447 | Not Implemented |
AS0510 # 05 Y:2021 | 05 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $6,879 | $560 | Not Implemented |
AS0510 # 04 Y:2021 | 04 | 2021 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $7,800 | $453 | Not Implemented |
AS0510 # 03 Y:2021 | 03 | 2021 | INSTALL SPECTRAL REFLECTORS / DELAMP | $13,978 | $9,244 | Implemented |
AS0510 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,025 | $18,448 | Not Implemented |
AS0497 # 06 Y:2021 | 06 | 2021 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,560 | $453 | Not Implemented |
AS0497 # 04 Y:2021 | 04 | 2021 | INSTALL SPECTRAL REFLECTORS / DELAMP | $3,053 | $678 | Implemented |
AS0497 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,067 | $104,184 | Implemented |
AS0497 # 05 Y:2021 | 05 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,227 | $8,870 | Implemented |
AS0497 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,810 | $9,023 | Implemented |
AS0497 # 10 Y:2021 | 10 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $152 | $287 | Implemented |
AS0497 # 09 Y:2021 | 09 | 2021 | INSTALL OCCUPANCY SENSORS | $722 | $569 | Implemented |
AS0497 # 03 Y:2021 | 03 | 2021 | COMBINE UTILITY METERS | $4,314 | $200 | Not Implemented |
AS0497 # 07 Y:2021 | 07 | 2021 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $978 | $315 | Implemented |
AS0497 # 08 Y:2021 | 08 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $926 | $250 | Implemented |
AS0456 # 04 Y:2018 | 04 | 2018 | OPTIMIZE PLANT POWER FACTOR | $30,900 | $16,614 | Not Implemented |
AS0456 # 03 Y:2018 | 03 | 2018 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $46,649 | $220,160 | Not Implemented |