IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20,208

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TT0202 # 05 Y:2017 05 2017 UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS $3,800 $1,200 Not Implemented
TT0202 # 06 Y:2017 06 2017 DEVELOP A REPAIR/REPLACE POLICY $403 $678 Implemented
TT0202 # 07 Y:2017 07 2017 INSTALL TIMERS AND/OR THERMOSTATS $197 $100 Implemented
UD0978 # 01 Y:2017 01 2017 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,058 $0 Not Implemented
UD0978 # 02 Y:2017 02 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,107 $1,000 Not Implemented
UD0978 # 03 Y:2017 03 2017 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES $1,562 $1,000 Not Implemented
UD0978 # 04 Y:2017 04 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $79,415 $79,850 Not Implemented
UD0978 # 05 Y:2017 05 2017 ADD AREA LIGHTING SWITCHES $2,220 $180 Not Implemented
UD0978 # 06 Y:2017 06 2017 USE OPTIMUM THICKNESS INSULATION $86,982 $91,480 Not Implemented
UD0978 # 07 Y:2017 07 2017 MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS $37,937 $100,000 Not Implemented
UD0978 # 08 Y:2017 08 2017 COVER OPEN TANKS $7,466 $5,000 Not Implemented
UD0978 # 09 Y:2017 09 2017 ADJUST BURNERS FOR EFFICIENT OPERATION $562 $0 Not Implemented
OR0693 # 01 Y:2017 01 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,809 $500 Not Implemented
OR0693 # 02 Y:2017 02 2017 RECOVER WASTE HEAT FROM EQUIPMENT $5,614 $2,800 Not Implemented
OR0693 # 03 Y:2017 03 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $27,216 $28,216 Not Implemented
OR0693 # 04 Y:2017 04 2017 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $45,260 $144,180 Not Implemented
OR0692 # 01 Y:2017 01 2017 REDUCE FLUID FLOW RATES $26,801 $7,395 Not Implemented
OR0692 # 02 Y:2017 02 2017 UTILIZE A LESS EXPENSIVE COOLING METHOD $2,636 $3,060 Not Implemented
OR0692 # 03 Y:2017 03 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,299 $3,670 Not Implemented
SF0511 # 01 Y:2017 01 2017 REPAIR AND ELIMINATE STEAM LEAKS $2,043 $0 Implemented
SF0511 # 02 Y:2017 02 2017 REDUCE VENTILATION AIR $1,680 $0 Implemented
SF0511 # 03 Y:2017 03 2017 COVER OPEN TANKS $2,660 $1,059 Implemented
SF0511 # 04 Y:2017 04 2017 INSULATE BARE EQUIPMENT $824 $1,526 Implemented
SF0511 # 05 Y:2017 05 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,786 $5,219 Implemented
MZ0240 # 01 Y:2017 01 2017 RECOVER WASTE HEAT FROM EQUIPMENT $7,020 $6,000 Implemented