IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20,208

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0084 # 04 Y:1990 04 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $282 $606 Implemented
AM0084 # 05 Y:1990 05 1990 INSTALL SET-BACK TIMERS $270 $0 Implemented
AM0084 # 06 Y:1990 06 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $105 $0 Implemented
AM0084 # 07 Y:1990 07 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $90 $0 Implemented
AM0085 # 01 Y:1990 01 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,500 $9,570 Implemented
AM0085 # 02 Y:1990 02 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,530 $7,140 Implemented
AM0085 # 03 Y:1990 03 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,330 $960 Implemented
AM0085 # 04 Y:1990 04 1990 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $660 $0 Implemented
AM0085 # 05 Y:1990 05 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $86 $74 Implemented
AM0085 # 06 Y:1990 06 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $423 $0 Not Implemented
AM0085 # 07 Y:1990 07 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $407 $480 Implemented
AM0085 # 08 Y:1990 08 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $400 $0 Not Implemented
AM0085 # 09 Y:1990 09 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $240 $0 Implemented
AM0085 # 10 Y:1990 10 1990 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $210 $200 Implemented
AM0085 # 11 Y:1990 11 1990 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $160 $0 Implemented
CO0174 # 01 Y:1990 01 1990 INSULATE BARE EQUIPMENT $2,600 $2,900 Not Implemented
CO0174 # 02 Y:1990 02 1990 INSTALL / REPAIR INSULATION ON STEAM LINES $760 $2,360 Not Implemented
CO0174 # 03 Y:1990 03 1990 COVER OPEN TANKS $761 $1,200 Not Implemented
CO0174 # 04 Y:1990 04 1990 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,055 $1,000 Not Implemented
CO0174 # 05 Y:1990 05 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $175 $74 Not Implemented
CO0174 # 06 Y:1990 06 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $380 $300 Not Implemented
CO0174 # 07 Y:1990 07 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $22 $105 Not Implemented
AM0081 # 01 Y:1990 01 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $15,096 $36,735 Implemented
AM0081 # 02 Y:1990 02 1990 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $8,627 $8,575 Implemented
AM0081 # 03 Y:1990 03 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,400 $1,000 Implemented