Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
730
matching recommendationsSIC | 343 | Plumbing And Heating, Except Electric |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0365 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $267,134 | $875,396 | n/a |
MZ0365 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,741 | $805 | n/a |
MZ0365 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,558 | $75,320 | n/a |
MZ0365 # 06 Y:2024 | 06 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,036 | $6,500 | n/a |
MZ0365 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,949 | $1,000 | n/a |
MZ0365 # 04 Y:2024 | 04 | 2024 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $96 | $520 | n/a |
IC0305 # 09 Y:2024 | 09 | 2024 | INSTALL OCCUPANCY SENSORS | $677 | $0 | n/a |
IC0305 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,071 | $5,184 | n/a |
IC0305 # 08 Y:2024 | 08 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $241 | $0 | n/a |
IC0305 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $24,798 | $190,030 | n/a |
IC0305 # 02 Y:2024 | 02 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $28,145 | $2,500 | n/a |
IC0305 # 05 Y:2024 | 05 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $1,126 | $3,467 | n/a |
IC0305 # 01 Y:2024 | 01 | 2024 | INCREASE AMOUNT OF CONDENSATE RETURNED | $8,515 | $18,062 | n/a |
IC0305 # 10 Y:2024 | 10 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,048 | $5,899 | n/a |
IC0305 # 07 Y:2024 | 07 | 2024 | INSULATE BARE EQUIPMENT | $1,737 | $2,801 | n/a |
IC0305 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,506 | $0 | n/a |
IC0305 # 12 Y:2024 | 12 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,840 | $2,566 | n/a |
IC0305 # 11 Y:2024 | 11 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $271 | $1,572 | n/a |
UA0283 # 11 Y:2023 | 11 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,688 | $31,108 | n/a |
UA0283 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $416,153 | $3,377,796 | n/a |
UA0283 # 10 Y:2023 | 10 | 2023 | USE SYNTHETIC LUBRICANT | $6,907 | $21,930 | n/a |
UA0283 # 08 Y:2023 | 08 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,686 | $750 | n/a |
UA0283 # 09 Y:2023 | 09 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,911 | $8,591 | n/a |
UA0283 # 05 Y:2023 | 05 | 2023 | PAY BILLS ON TIME TO AVOID LATE FEES | $21,298 | $0 | n/a |
UA0283 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,247 | $22,655 | n/a |