Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,509
matching recommendationsSIC | 344 | Fabricated Structural Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0157 # 04 Y:1992 | 04 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $50 | $173 | Not Implemented |
SD0022 # 01 Y:1992 | 01 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,880 | $1,817 | Implemented |
SD0022 # 02 Y:1992 | 02 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,846 | $2,000 | Implemented |
SD0022 # 03 Y:1992 | 03 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $591 | $15 | Implemented |
SD0022 # 04 Y:1992 | 04 | 1992 | COVER OPEN TANKS | $516 | $169 | Implemented |
SD0022 # 05 Y:1992 | 05 | 1992 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $158 | $138 | Implemented |
SD0022 # 06 Y:1992 | 06 | 1992 | INSULATE BARE EQUIPMENT | $138 | $122 | Implemented |
SD0022 # 07 Y:1992 | 07 | 1992 | KEEP LAMPS AND REFLECTORS CLEAN | $24,184 | $51,124 | Not Implemented |
SD0022 # 08 Y:1992 | 08 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $584 | $999 | Implemented |
SD0022 # 09 Y:1992 | 09 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,496 | $2,200 | Implemented |
SD0022 # 10 Y:1992 | 10 | 1992 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $1,222 | $0 | Implemented |
UF0035 # 01 Y:1992 | 01 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $208 | $514 | Implemented |
UF0035 # 02 Y:1992 | 02 | 1992 | INSTALL SPECTRAL REFLECTORS / DELAMP | $3,537 | $6,210 | Implemented |
UF0035 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $94 | $1,630 | Implemented |
UF0035 # 04 Y:1992 | 04 | 1992 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $136 | $220 | Not Implemented |
UF0035 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $448 | $3,944 | Not Implemented |
UF0035 # 06 Y:1992 | 06 | 1992 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,487 | $1,500 | Not Implemented |
IA0017 # 01 Y:1992 | 01 | 1992 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,858 | $700 | Implemented |
IA0017 # 02 Y:1992 | 02 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,694 | $2,000 | Not Implemented |
IA0017 # 03 Y:1992 | 03 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,603 | $500 | Implemented |
IA0017 # 04 Y:1992 | 04 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,470 | $0 | Not Implemented |
IA0017 # 05 Y:1992 | 05 | 1992 | INSTALL SET-BACK TIMERS | $402 | $400 | Not Implemented |
IA0017 # 06 Y:1992 | 06 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $184 | $29 | Not Implemented |
IA0017 # 07 Y:1992 | 07 | 1992 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,834 | $22,000 | Implemented |
IA0017 # 08 Y:1992 | 08 | 1992 | REDUCE VENTILATION AIR | $3,955 | $3,150 | Not Implemented |