Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
859
matching recommendationsSIC | 3442 | Metal Doors, Sash, And Trim |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0387 # 02 Y:1992 | 02 | 1992 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $35,120 | $38,000 | Implemented |
UD0387 # 03 Y:1992 | 03 | 1992 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $4,668 | $0 | Implemented |
UD0387 # 04 Y:1992 | 04 | 1992 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,850 | $1,000 | Implemented |
UD0387 # 05 Y:1992 | 05 | 1992 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,875 | $2,000 | Implemented |
UD0387 # 06 Y:1992 | 06 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $891 | $0 | Not Implemented |
UD0387 # 07 Y:1992 | 07 | 1992 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,594 | $1,000 | Implemented |
HO0024 # 01 Y:1992 | 01 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $909 | $290 | Implemented |
HO0024 # 02 Y:1992 | 02 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $547 | $91 | Implemented |
HO0024 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,060 | $4,900 | Implemented |
HO0024 # 04 Y:1992 | 04 | 1992 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,887 | $2,000 | Not Implemented |
HO0024 # 05 Y:1992 | 05 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $208 | $800 | Not Implemented |
HO0024 # 06 Y:1992 | 06 | 1992 | COMBINE UTILITY METERS | $6,926 | $2,000 | Implemented |
HO0024 # 07 Y:1992 | 07 | 1992 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,300 | $200 | Not Implemented |
OR0157 # 01 Y:1992 | 01 | 1992 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $628 | $120 | Implemented |
OR0157 # 02 Y:1992 | 02 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $287 | $300 | Implemented |
OR0157 # 03 Y:1992 | 03 | 1992 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $203 | $640 | Implemented |
OR0157 # 04 Y:1992 | 04 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $50 | $173 | Not Implemented |
SD0003 # 01 Y:1991 | 01 | 1991 | COVER OPEN TANKS | $1,090 | $256 | Not Implemented |
SD0003 # 02 Y:1991 | 02 | 1991 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $7,229 | $1,500 | Not Implemented |
SD0003 # 03 Y:1991 | 03 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $102 | $80 | Not Implemented |
SD0003 # 04 Y:1991 | 04 | 1991 | INSTALL SET-BACK TIMERS | $4,991 | $10,350 | Not Implemented |
SD0003 # 05 Y:1991 | 05 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $4,131 | $9,652 | Not Implemented |
SD0003 # 06 Y:1991 | 06 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $2,030 | $5,280 | Not Implemented |
SD0003 # 07 Y:1991 | 07 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,494 | $0 | Not Implemented |
SD0003 # 08 Y:1991 | 08 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,990 | $600 | Not Implemented |