Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,060
matching recommendationsSIC | 345 | Screw Machine Products, Bolts, Etc. |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0212 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,829 | $2,021 | Not Implemented |
WI0212 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $488 | $1,760 | Not Implemented |
WI0212 # 05 Y:1994 | 05 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $978 | $1,329 | Not Implemented |
WI0212 # 06 Y:1994 | 06 | 1994 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $585 | $370 | Implemented |
WI0212 # 07 Y:1994 | 07 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $543 | $464 | Not Implemented |
WI0212 # 08 Y:1994 | 08 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $346 | $960 | Not Implemented |
WI0212 # 09 Y:1994 | 09 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $147 | $0 | Not Implemented |
WI0212 # 10 Y:1994 | 10 | 1994 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,000 | $7,000 | Implemented |
UL0106 # 03 Y:1994 | 03 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,428 | $3,203 | Not Implemented |
UL0106 # 04 Y:1994 | 04 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,326 | $2,000 | Not Implemented |
UL0106 # 05 Y:1994 | 05 | 1994 | OPTIMIZE PLANT POWER FACTOR | $626 | $1,084 | Not Implemented |
UL0106 # 06 Y:1994 | 06 | 1994 | OPTIMIZE PLANT POWER FACTOR | $2,436 | $9,204 | Not Implemented |
UL0106 # 01 Y:1994 | 01 | 1994 | INSULATE BARE EQUIPMENT | $243 | $36 | Not Implemented |
UL0106 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,971 | $8,620 | Not Implemented |
WI0207 # 01 Y:1994 | 01 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,556 | $6,000 | Implemented |
WI0207 # 02 Y:1994 | 02 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,229 | $3,840 | Not Implemented |
WI0207 # 03 Y:1994 | 03 | 1994 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,970 | $600 | Not Implemented |
WI0207 # 04 Y:1994 | 04 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,382 | $8,346 | Implemented |
WI0207 # 05 Y:1994 | 05 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $325 | $0 | Not Implemented |
WI0207 # 06 Y:1994 | 06 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $186 | $528 | Not Implemented |
WI0207 # 07 Y:1994 | 07 | 1994 | COVER OPEN TANKS | $1,852 | $288 | Not Implemented |
WI0207 # 08 Y:1994 | 08 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $708 | $820 | Implemented |
WI0207 # 09 Y:1994 | 09 | 1994 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $408 | $0 | Not Implemented |
WI0207 # 10 Y:1994 | 10 | 1994 | RECYCLE CLEANING SOLVENT AND REUSE | $15,300 | $21,000 | Not Implemented |
WI0207 # 11 Y:1994 | 11 | 1994 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $7,000 | $10,000 | Not Implemented |