IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

23

matching recommendations
Reset
SIC 345 Screw Machine Products, Bolts, Etc.
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0167 # 02 Y:1989 02 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,010 $150 Implemented
CO0167 # 03 Y:1989 03 1989 RECOVER WASTE HEAT FROM EQUIPMENT $1,800 $2,500 Not Implemented
CO0167 # 04 Y:1989 04 1989 INSTALL TIMERS AND/OR THERMOSTATS $1,345 $1,000 Not Implemented
CO0167 # 05 Y:1989 05 1989 USE DIRECT AIR SUPPLY TO EXHAUST HOODS $1,200 $1,900 Not Implemented
CO0167 # 06 Y:1989 06 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $455 $335 Implemented
CO0167 # 07 Y:1989 07 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $105 $315 Implemented
CO0167 # 08 Y:1989 08 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $870 $200 Implemented
CO0167 # 09 Y:1989 09 1989 INSULATE BARE EQUIPMENT $360 $290 Implemented
CO0167 # 01 Y:1989 01 1989 OPTIMIZE PLANT POWER FACTOR $6,740 $6,800 Implemented
AM0068 # 03 Y:1989 03 1989 INSTALL SET-BACK TIMERS $2,180 $0 Implemented
AM0068 # 06 Y:1989 06 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $330 $295 Implemented
AM0068 # 05 Y:1989 05 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $347 $97 Implemented
AM0068 # 04 Y:1989 04 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $890 $1,000 Implemented
AM0068 # 02 Y:1989 02 1989 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $9,210 $16,500 Implemented
AM0068 # 01 Y:1989 01 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $40,430 $24,600 Implemented
WI0051 # 01 Y:1989 01 1989 IMPROVE LUBRICATION PRACTICES $9,567 $0 Not Implemented
WI0051 # 02 Y:1989 02 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,458 $0 Implemented
WI0051 # 03 Y:1989 03 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,788 $5,246 Implemented
WI0051 # 04 Y:1989 04 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $12,672 $5,000 Not Implemented
WI0051 # 05 Y:1989 05 1989 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $13,401 $0 Implemented
WI0051 # 06 Y:1989 06 1989 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $100,358 $40,000 Not Implemented
WI0051 # 07 Y:1989 07 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $2,417 $5,000 Not Implemented
WI0051 # 08 Y:1989 08 1989 INSTALL TIMERS AND/OR THERMOSTATS $3,060 $14,250 Implemented