IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

258

matching recommendations
Reset
SIC 35 Industrial Machinery And Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MS0323 # 05 Y:2008 05 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $257 $450 Implemented
MS0323 # 04 Y:2008 04 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,492 $8,771 Implemented
MS0323 # 03 Y:2008 03 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,739 $3,030 Implemented
MS0323 # 02 Y:2008 02 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,013 $266 Implemented
MS0323 # 01 Y:2008 01 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,680 $26,178 Implemented
MS0312 # 04 Y:2007 04 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $551 $4,911 Not Implemented
MS0312 # 03 Y:2007 03 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,372 $135 Not Implemented
MS0312 # 02 Y:2007 02 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $19,170 $1,559 Not Implemented
MS0312 # 01 Y:2007 01 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $21,487 $38,702 Not Implemented
MS0260 # 07 Y:2004 07 2004 COVER OPEN TANKS $312 $68 Not Implemented
MS0260 # 06 Y:2004 06 2004 DISCONNECT BALLASTS $341 $408 Implemented
MS0260 # 05 Y:2004 05 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $811 $348 Implemented
MS0260 # 04 Y:2004 04 2004 INSTALL TIMERS AND/OR THERMOSTATS $3,685 $1,666 Not Implemented
MS0260 # 03 Y:2004 03 2004 MINIMIZE WATER USAGE $9,057 $107 Not Implemented
MS0260 # 02 Y:2004 02 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $12,850 $1,350 Not Implemented
MS0260 # 01 Y:2004 01 2004 CLEAR AND RENT EXISTING SPACE $28,604 $10,000 Not Implemented
MS0253 # 05 Y:2004 05 2004 BURN WASTE OIL FOR HEAT $703 $2,190 Not Implemented
MS0253 # 01 Y:2004 01 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,032 $11 Not Implemented
MS0253 # 02 Y:2004 02 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,649 $4,689 Not Implemented
MS0253 # 03 Y:2004 03 2004 USE RADIANT HEATER FOR SPOT HEATING $1,526 $4,000 Implemented
MS0253 # 04 Y:2004 04 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $853 $288 Implemented
MS0253 # 07 Y:2004 07 2004 CONVERT FROM BATCH OPERATION TO CONTINUOUS PROCESSING $336 $68 Not Implemented
MS0253 # 06 Y:2004 06 2004 INSTALL TIMERS AND/OR THERMOSTATS $480 $708 Not Implemented
MS0253 # 08 Y:2004 08 2004 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $198 $735 Implemented
MS0240 # 05 Y:2003 05 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,210 $228 Implemented