Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 3519 | Internal Combustion Engines, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0632 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,805 | $706 | Implemented |
WV0632 # 12 Y:2022 | 12 | 2022 | INSTALL OCCUPANCY SENSORS | $371 | $1,135 | Implemented |
WV0632 # 11 Y:2022 | 11 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $456 | $1,192 | Implemented |
WV0632 # 10 Y:2022 | 10 | 2022 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $669 | $3,115 | Implemented |
WV0632 # 09 Y:2022 | 09 | 2022 | DEVELOP A REPAIR/REPLACE POLICY | $714 | $1,638 | Implemented |
WV0632 # 08 Y:2022 | 08 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $727 | $92 | Implemented |
WV0632 # 07 Y:2022 | 07 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $865 | $2,227 | Not Implemented |
WV0632 # 06 Y:2022 | 06 | 2022 | INSULATE BARE EQUIPMENT | $1,112 | $1,037 | Implemented |
WV0632 # 05 Y:2022 | 05 | 2022 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,169 | $5,688 | Not Implemented |
WV0632 # 03 Y:2022 | 03 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $4,403 | $2,234 | Not Implemented |
WV0632 # 02 Y:2022 | 02 | 2022 | IMPROVE COMBUSTION CONTROL CAPABILITY | $5,035 | $3,423 | Implemented |
WV0632 # 01 Y:2022 | 01 | 2022 | MINIMIZE WATER USAGE | $12,558 | $11,644 | Not Implemented |
TT0279 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $43,670 | $43,750 | Implemented |
TT0279 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,432 | $4,000 | Not Implemented |
TT0279 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,957 | $250 | Not Implemented |
TT0279 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,514 | $12,000 | Not Implemented |
TT0279 # 02 Y:2022 | 02 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $12,173 | $63,875 | Not Implemented |