Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsSIC | 3571 | Electronic Computers |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0028 # 08 Y:1991 | 08 | 1991 | INSTALL SET-BACK TIMERS | $422 | $1,275 | Not Implemented |
AS0028 # 10 Y:1991 | 10 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $564 | $0 | Not Implemented |
AS0028 # 02 Y:1991 | 02 | 1991 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $3,454 | $20,000 | Not Implemented |
AS0028 # 01 Y:1991 | 01 | 1991 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $16,506 | $65,000 | Not Implemented |
AM0065 # 06 Y:1989 | 06 | 1989 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $640 | $2,750 | Not Implemented |
AM0065 # 05 Y:1989 | 05 | 1989 | REDUCE VENTILATION AIR | $778 | $1,950 | Not Implemented |
AM0065 # 04 Y:1989 | 04 | 1989 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,540 | $6,475 | Not Implemented |
AM0065 # 03 Y:1989 | 03 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $3,675 | $13,500 | Not Implemented |
AM0065 # 02 Y:1989 | 02 | 1989 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $4,000 | $4,000 | Not Implemented |
AM0065 # 01 Y:1989 | 01 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,893 | $418 | Implemented |
AT0056 # 07 Y:1986 | 07 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $738 | $0 | Implemented |
AT0056 # 01 Y:1986 | 01 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $966 | $626 | Implemented |
AT0056 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $107 | $180 | Not Implemented |
AT0056 # 03 Y:1986 | 03 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $295 | $250 | Not Implemented |
AT0056 # 04 Y:1986 | 04 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $604 | $100 | Not Implemented |
AT0056 # 05 Y:1986 | 05 | 1986 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,087 | $2,000 | Not Implemented |
AT0056 # 06 Y:1986 | 06 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $1,033 | $0 | Implemented |
AT0056 # 08 Y:1986 | 08 | 1986 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $6,965 | $1,000 | Not Implemented |
AT0056 # 09 Y:1986 | 09 | 1986 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $15,428 | $10,000 | Not Implemented |
CO0045 # 05 Y:1985 | 05 | 1985 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $440 | $300 | Implemented |
CO0045 # 01 Y:1985 | 01 | 1985 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $11,273 | $1,500 | Not Implemented |
CO0045 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,736 | $300 | Implemented |
CO0045 # 03 Y:1985 | 03 | 1985 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,875 | $200 | Not Implemented |
CO0045 # 04 Y:1985 | 04 | 1985 | TURN OFF EQUIPMENT WHEN NOT IN USE | $559 | $400 | Not Implemented |
CO0045 # 06 Y:1985 | 06 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,215 | $6,411 | Implemented |