IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,249

matching recommendations
Reset
SIC 359 Industrial Machinery, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0094 # 02 Y:1990 02 1990 INSTALL SET-BACK TIMERS $8,700 $450 Implemented
AM0094 # 03 Y:1990 03 1990 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $6,807 $7,920 Implemented
AM0094 # 04 Y:1990 04 1990 INSTALL / REPAIR INSULATION ON STEAM LINES $2,870 $3,160 Implemented
AM0094 # 05 Y:1990 05 1990 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $2,260 $675 Implemented
AM0094 # 06 Y:1990 06 1990 IMPROVE LUBRICATION PRACTICES $670 $0 Implemented
AM0094 # 07 Y:1990 07 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $715 $500 Implemented
AM0094 # 08 Y:1990 08 1990 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $580 $270 Implemented
AM0094 # 09 Y:1990 09 1990 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $260 $0 Implemented
OK0306 # 01 Y:1990 01 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,969 $27,903 Not Implemented
OK0306 # 02 Y:1990 02 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $859 $640 Not Implemented
OK0306 # 03 Y:1990 03 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $110 $102 Implemented
OK0306 # 04 Y:1990 04 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $18,384 $0 Not Implemented
OK0306 # 05 Y:1990 05 1990 OPTIMIZE PLANT POWER FACTOR $10,716 $16,250 Not Implemented
OK0306 # 06 Y:1990 06 1990 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $810 $1,300 Implemented
OK0306 # 07 Y:1990 07 1990 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,419 $0 Not Implemented
OK0306 # 08 Y:1990 08 1990 INSTALL TIMERS AND/OR THERMOSTATS $493 $150 Implemented
WI0076 # 01 Y:1990 01 1990 SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS $19,921 $0 Not Implemented
WI0076 # 02 Y:1990 02 1990 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,064 $12,726 Not Implemented
WI0076 # 03 Y:1990 03 1990 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,784 $0 Not Implemented
WI0076 # 04 Y:1990 04 1990 INSTALL SET-BACK TIMERS $1,952 $1,000 Not Implemented
WI0076 # 05 Y:1990 05 1990 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,725 $3,750 Not Implemented
WI0076 # 06 Y:1990 06 1990 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,725 $0 Not Implemented
WI0076 # 07 Y:1990 07 1990 INSTALL TIMERS AND/OR THERMOSTATS $1,709 $500 Not Implemented
WI0076 # 08 Y:1990 08 1990 RECOVER WASTE HEAT FROM EQUIPMENT $1,107 $1,000 Not Implemented
WI0076 # 09 Y:1990 09 1990 INSTALL STORM WINDOWS AND DOORS $482 $1,440 Not Implemented