Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
245
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0337 # 06 Y:2023 | 06 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $150,000 | $75,650 | Implemented |
MZ0337 # 02 Y:2023 | 02 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,106 | $2,400 | Implemented |
MZ0337 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,895 | $9,731 | Implemented |
MZ0337 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,882 | $6,873 | Implemented |
MZ0337 # 03 Y:2023 | 03 | 2023 | USE PHOTOCELL CONTROLS | $314 | $100 | Implemented |
MZ0331 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,162 | $25,757 | Implemented |
MZ0331 # 04 Y:2022 | 04 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,985 | $29,286 | Implemented |
MZ0331 # 06 Y:2022 | 06 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $31,613 | $98,280 | Implemented |
MZ0331 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,037 | $46,350 | Implemented |
MZ0331 # 03 Y:2022 | 03 | 2022 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $91,773 | $9,040 | Implemented |
MZ0318 # 01 Y:2021 | 01 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $261 | $1,600 | Implemented |
MZ0318 # 05 Y:2021 | 05 | 2021 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $168 | $130 | Implemented |
MZ0318 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,004 | $200 | Implemented |
MZ0318 # 04 Y:2021 | 04 | 2021 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $29,334 | $6,436 | Implemented |
MZ0318 # 02 Y:2021 | 02 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $248 | $320 | Implemented |
MZ0318 # 06 Y:2021 | 06 | 2021 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $4,616 | $0 | Implemented |
MZ0252 # 06 Y:2018 | 06 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $516 | $50 | Implemented |
MZ0252 # 01 Y:2018 | 01 | 2018 | INSTALL SPECTRAL REFLECTORS / DELAMP | $4,011 | $540 | Implemented |
MZ0252 # 02 Y:2018 | 02 | 2018 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,478 | $32,500 | Implemented |
MZ0252 # 05 Y:2018 | 05 | 2018 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $65,281 | $50,000 | Implemented |
MZ0252 # 04 Y:2018 | 04 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,159 | $0 | Implemented |
MZ0237 # 08 Y:2017 | 08 | 2017 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $22,338 | $0 | Implemented |
MZ0237 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $599 | $50 | Implemented |
MZ0237 # 01 Y:2017 | 01 | 2017 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,793 | $0 | Implemented |
MZ0237 # 07 Y:2017 | 07 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $69 | $0 | Implemented |