Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,701
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0558 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $896 | $2,000 | Not Implemented |
LE0558 # 05 Y:2024 | 05 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,840 | $18,014 | Implemented |
LE0558 # 06 Y:2024 | 06 | 2024 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $7,995 | $37,000 | Implemented |
LE0558 # 07 Y:2024 | 07 | 2024 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $474 | $2,500 | Implemented |
CW0130 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,562 | $17,397 | n/a |
CW0130 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $4,196 | $2,050 | n/a |
CW0130 # 03 Y:2024 | 03 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $17,298 | $8,391 | n/a |
CW0130 # 04 Y:2024 | 04 | 2024 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $202 | $424 | n/a |
CW0130 # 05 Y:2024 | 05 | 2024 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $7,210 | $13,000 | n/a |
CW0130 # 06 Y:2024 | 06 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $1,786 | $6,750 | n/a |
WM0211 # 01 Y:2024 | 01 | 2024 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $7,114 | $700 | Implemented |
WM0211 # 02 Y:2024 | 02 | 2024 | USE RADIANT HEATER FOR SPOT HEATING | $5,517 | $16,193 | Not Implemented |
WM0211 # 03 Y:2024 | 03 | 2024 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,617 | $9,500 | Implemented |
WM0211 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,148 | $150 | Implemented |
WM0211 # 05 Y:2024 | 05 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $216 | $345 | Implemented |
WM0211 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $110 | $0 | Not Implemented |
LE0557 # 01 Y:2024 | 01 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $279,544 | $0 | Implemented |
LE0557 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $87,150 | $3,000 | Not Implemented |
LE0557 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,494 | $100 | Implemented |
LE0557 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $35,783 | $9,500 | Not Implemented |
LE0557 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $197,906 | $323,780 | Implemented |
LE0557 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $291,977 | $600,000 | Not Implemented |
LE0557 # 07 Y:2024 | 07 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,463 | $29,000 | Not Implemented |
LE0557 # 08 Y:2024 | 08 | 2024 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $9,250 | $37,000 | Not Implemented |
MI0434 # 01 Y:2023 | 01 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $29,836 | $550 | Implemented |