IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

48

matching recommendations
Reset
SIC 364 Electric Lighting And Wiring Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MO0044 # 04 Y:1991 04 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,326 $0 Implemented
MO0044 # 03 Y:1991 03 1991 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,455 $20 Implemented
MO0044 # 09 Y:1991 09 1991 INSTALL STORM WINDOWS AND DOORS $7,704 $5,952 Implemented
MO0044 # 02 Y:1991 02 1991 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,584 $561 Implemented
MO0044 # 01 Y:1991 01 1991 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $20,836 $26,565 Implemented
MO0044 # 05 Y:1991 05 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,260 $2,690 Implemented
MO0044 # 06 Y:1991 06 1991 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $271 $411 Implemented
MO0044 # 08 Y:1991 08 1991 IMPROVE LUBRICATION PRACTICES $2,256 $528 Implemented
MO0044 # 07 Y:1991 07 1991 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $612 $0 Implemented
KU0354 # 04 Y:1991 04 1991 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $825 $200 Implemented
KU0354 # 01 Y:1991 01 1991 INSTALL TIMERS AND/OR THERMOSTATS $7,348 $1,000 Implemented
KU0354 # 02 Y:1991 02 1991 RECOVER WASTE HEAT FROM EQUIPMENT $988 $705 Implemented
KU0354 # 05 Y:1991 05 1991 INSTALL SET-BACK TIMERS $570 $330 Implemented
KU0354 # 03 Y:1991 03 1991 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $275 $100 Implemented
AS0031 # 08 Y:1991 08 1991 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $5,751 $0 Not Implemented
AS0031 # 10 Y:1991 10 1991 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $150,310 $0 Not Implemented
AS0031 # 09 Y:1991 09 1991 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $4,763 $3,054 Not Implemented
AS0031 # 07 Y:1991 07 1991 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,863 $3,333 Not Implemented
AS0031 # 06 Y:1991 06 1991 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $653 $933 Not Implemented
AS0031 # 05 Y:1991 05 1991 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $7,847 $40 Not Implemented
AS0031 # 04 Y:1991 04 1991 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,253 $4,496 Not Implemented
AS0031 # 03 Y:1991 03 1991 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM $7,962 $20,000 Not Implemented
AS0031 # 02 Y:1991 02 1991 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $11,865 $50,000 Not Implemented
AS0031 # 01 Y:1991 01 1991 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT $54,844 $127,000 Not Implemented
RU0107 # 05 Y:1991 05 1991 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $217 $59 Not Implemented