IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

32

matching recommendations
Reset
SIC 3644 Noncurrent-carrying Wiring Devices
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0451 # 01 Y:2004 01 2004 OPTIMIZE PLANT POWER FACTOR $13,040 $12,960 Not Implemented
TA0021 # 01 Y:2002 01 2002 INSTALL / REPAIR INSULATION ON STEAM LINES $11,450 $5,883 Implemented
TA0021 # 02 Y:2002 02 2002 INCREASE AMOUNT OF CONDENSATE RETURNED $9,736 $19,010 Not Implemented
TA0021 # 03 Y:2002 03 2002 REPAIR AND ELIMINATE STEAM LEAKS $6,110 $190 Implemented
TA0021 # 04 Y:2002 04 2002 INSULATE BARE EQUIPMENT $864 $504 Implemented
TA0021 # 05 Y:2002 05 2002 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $535 $0 Implemented
TA0021 # 06 Y:2002 06 2002 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $103 $0 Implemented