Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
40
matching recommendationsSIC | 3674 | Semiconductors And Related Devices |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0315 # 01 Y:1994 | 01 | 1994 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $7,950 | $30 | Implemented |
CO0315 # 02 Y:1994 | 02 | 1994 | USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES | $1,290 | $0 | Not Implemented |
CO0315 # 03 Y:1994 | 03 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,070 | $1,770 | Implemented |
CO0315 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,010 | $5,310 | Implemented |
CO0315 # 05 Y:1994 | 05 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $630 | $650 | Not Implemented |
CO0315 # 06 Y:1994 | 06 | 1994 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $410 | $2,000 | Not Implemented |
SF0029 # 06 Y:1994 | 06 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $623 | $540 | Not Implemented |
SF0029 # 05 Y:1994 | 05 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $338 | $600 | Not Implemented |
SF0029 # 04 Y:1994 | 04 | 1994 | INSTALL OCCUPANCY SENSORS | $918 | $1,316 | Implemented |
SF0029 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $440 | $123 | Not Implemented |
SF0029 # 02 Y:1994 | 02 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,033 | $0 | Not Implemented |
SF0029 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,462 | $10,810 | Implemented |
KG0003 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,276 | $9,920 | Implemented |
KG0003 # 07 Y:1994 | 07 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $372 | $1,186 | Implemented |
KG0003 # 06 Y:1994 | 06 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $126 | $155 | Not Implemented |
KG0003 # 05 Y:1994 | 05 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,629 | $2,500 | Implemented |
KG0003 # 04 Y:1994 | 04 | 1994 | INSULATE BARE EQUIPMENT | $1,863 | $100 | Not Implemented |
KG0003 # 03 Y:1994 | 03 | 1994 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $2,257 | $2,200 | Implemented |
KG0003 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,639 | $2,314 | Not Implemented |
SD0079 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,415 | $1,020 | Not Implemented |
SD0079 # 14 Y:1994 | 14 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $957 | $420 | Not Implemented |
SD0079 # 13 Y:1994 | 13 | 1994 | INSTALL OCCUPANCY SENSORS | $1,277 | $3,380 | Not Implemented |
SD0079 # 12 Y:1994 | 12 | 1994 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $105 | $50 | Not Implemented |
SD0079 # 11 Y:1994 | 11 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $114 | $117 | Not Implemented |
SD0079 # 10 Y:1994 | 10 | 1994 | INSTALL SPECTRAL REFLECTORS / DELAMP | $334 | $568 | Not Implemented |