Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,374
matching recommendationsSIC | 371 | Motor Vehicles And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0489 # 05 Y:1993 | 05 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,488 | $380 | Not Implemented |
TN0489 # 06 Y:1993 | 06 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $500 | $480 | Implemented |
TN0489 # 07 Y:1993 | 07 | 1993 | OPTIMIZE PLANT POWER FACTOR | $7,337 | $13,300 | Implemented |
UF0052 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,646 | $2,689 | Not Implemented |
UF0052 # 02 Y:1993 | 02 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,434 | $2,416 | Not Implemented |
UF0052 # 03 Y:1993 | 03 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $112 | $175 | Not Implemented |
UF0052 # 04 Y:1993 | 04 | 1993 | USE POWER DURING OFF-PEAK PERIODS | $4,913 | $0 | Not Implemented |
UF0052 # 05 Y:1993 | 05 | 1993 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $356 | $1,400 | Not Implemented |
IA0039 # 01 Y:1992 | 01 | 1992 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $6,617 | $15,000 | Not Implemented |
IA0039 # 02 Y:1992 | 02 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $744 | $600 | Not Implemented |
IA0039 # 03 Y:1992 | 03 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,769 | $360 | Not Implemented |
IA0039 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $322 | $73 | Not Implemented |
KU0388 # 01 Y:1992 | 01 | 1992 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $24,157 | $0 | Not Implemented |
KU0388 # 02 Y:1992 | 02 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,781 | $17,843 | Implemented |
KU0388 # 03 Y:1992 | 03 | 1992 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,530 | $3,400 | Implemented |
KU0388 # 04 Y:1992 | 04 | 1992 | ISOLATE STEAM LINES TO AVOID HEATING AIR CONDITIONED AREAS | $1,078 | $59,000 | Implemented |
KU0388 # 05 Y:1992 | 05 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $1,892 | $925 | Implemented |
KU0388 # 06 Y:1992 | 06 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,155 | $630 | Implemented |
KU0388 # 07 Y:1992 | 07 | 1992 | USE COMPRESSOR AIR FILTERS | $851 | $0 | Implemented |
KU0388 # 08 Y:1992 | 08 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $182 | $480 | Implemented |
KU0388 # 09 Y:1992 | 09 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $172 | $0 | Implemented |
KU0388 # 10 Y:1992 | 10 | 1992 | INSTALL SET-BACK TIMERS | $515 | $900 | Implemented |
KU0388 # 11 Y:1992 | 11 | 1992 | INSTALL SET-BACK TIMERS | $281 | $91 | Not Implemented |
IA0024 # 01 Y:1992 | 01 | 1992 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,552 | $51,000 | Implemented |
IA0024 # 02 Y:1992 | 02 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $8,634 | $3,600 | Not Implemented |