Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
164
matching recommendationsSIC | 3714 | Motor Vehicle Parts And Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
HO0124 # 04 Y:1995 | 04 | 1995 | USE RADIANT HEATER FOR SPOT HEATING | $714 | $2,400 | Implemented |
HO0124 # 03 Y:1995 | 03 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $357 | $0 | Implemented |
HO0124 # 02 Y:1995 | 02 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $51 | $150 | Not Implemented |
HO0124 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,051 | $11,011 | Implemented |
AR0074 # 06 Y:1995 | 06 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $139,091 | $55,000 | Not Implemented |
AR0074 # 10 Y:1995 | 10 | 1995 | MAINTAIN MACHINES TO REDUCE LEAKS | $3,240 | $1,000 | Implemented |
AR0074 # 05 Y:1995 | 05 | 1995 | OPTIMIZE PLANT POWER FACTOR | $5,669 | $13,220 | Not Implemented |
AR0074 # 04 Y:1995 | 04 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,547 | $25 | Implemented |
AR0074 # 03 Y:1995 | 03 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,864 | $350 | Implemented |
AR0074 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,013 | $14,650 | Implemented |
AR0074 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $800 | $584 | Implemented |
AR0074 # 07 Y:1995 | 07 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $408 | $0 | Implemented |
AR0074 # 08 Y:1995 | 08 | 1995 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $18,582 | $500 | Implemented |
AR0074 # 09 Y:1995 | 09 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,696 | $200 | Implemented |
UF0131 # 07 Y:1995 | 07 | 1995 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $8,226 | $11,400 | Not Implemented |
UF0131 # 09 Y:1995 | 09 | 1995 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $110,283 | $250,000 | Not Implemented |
UF0131 # 05 Y:1995 | 05 | 1995 | DISCONNECT BALLASTS | $553 | $1,400 | Not Implemented |
UF0131 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,115 | $14,659 | Implemented |
UF0131 # 10 Y:1995 | 10 | 1995 | USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME | $85,495 | $8,000 | Implemented |
UF0131 # 08 Y:1995 | 08 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $845 | $350 | Implemented |
UF0131 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,967 | $13,352 | Implemented |
UF0131 # 02 Y:1995 | 02 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,319 | $204 | Not Implemented |
UF0131 # 06 Y:1995 | 06 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,001 | $1,116 | Not Implemented |
UF0131 # 04 Y:1995 | 04 | 1995 | INSTALL OCCUPANCY SENSORS | $677 | $1,152 | Not Implemented |
BD0039 # 06 Y:1995 | 06 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $182 | $305 | Implemented |