Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,491

matching recommendations
Reset
SIC 372 Aircraft And Parts
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0142 # 02 Y:2019 02 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,981 $14,585 Implemented
UU0142 # 03 Y:2019 03 2019 OPTIMIZE PLANT POWER FACTOR $1,742 $2,500 Not Implemented
UU0142 # 04 Y:2019 04 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,661 $0 Implemented
UU0142 # 05 Y:2019 05 2019 INSTALL OCCUPANCY SENSORS $1,532 $0 Implemented
UU0142 # 06 Y:2019 06 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $810 $129 Not Implemented
UU0142 # 07 Y:2019 07 2019 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $288 $100 Implemented
MZ0264 # 01 Y:2019 01 2019 TURN OFF EQUIPMENT WHEN NOT IN USE $1,108 $2,050 Implemented
MZ0264 # 02 Y:2019 02 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,749 $1,328 Not Implemented
MZ0264 # 03 Y:2019 03 2019 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $3,139 $1,050 Implemented
MZ0264 # 04 Y:2019 04 2019 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,987 $1,460 Implemented
MZ0264 # 05 Y:2019 05 2019 INSTALL OCCUPANCY SENSORS $1,844 $710 Not Implemented
MZ0264 # 06 Y:2019 06 2019 RECOVER WASTE HEAT FROM EQUIPMENT $1,401 $810 Not Implemented
MZ0264 # 07 Y:2019 07 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $975 $836 Implemented
MZ0264 # 08 Y:2019 08 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $420 $274 Implemented
OK0996 # 01 Y:2018 01 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $32,265 $25,906 Implemented
OK0996 # 02 Y:2018 02 2018 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $18,485 $22,966 Not Implemented
OK0996 # 03 Y:2018 03 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $18,799 $9,162 Not Implemented
OK0996 # 04 Y:2018 04 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,536 $2,095 Not Implemented
OK0996 # 05 Y:2018 05 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,396 $0 Not Implemented
OK0996 # 06 Y:2018 06 2018 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,466 $610 Not Implemented
OK0994 # 01 Y:2018 01 2018 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,051 $590 Implemented
OK0994 # 02 Y:2018 02 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,833 $8,422 Implemented
OK0994 # 03 Y:2018 03 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $15,575 $29,950 Implemented
OK0995 # 01 Y:2018 01 2018 OPTIMIZE PLANT POWER FACTOR $32,860 $45,285 Not Implemented
OK0995 # 02 Y:2018 02 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,425 $19,203 Implemented