Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
155
matching recommendationsSIC | 38 | Instruments And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1053 # 07 Y:2023 | 07 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,097 | $110,000 | Implemented |
UD1053 # 08 Y:2023 | 08 | 2023 | INSTALL OCCUPANCY SENSORS | $7,370 | $110,000 | Implemented |
UD1053 # 04 Y:2023 | 04 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,943 | $0 | Not Implemented |
UD1053 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $95,100 | $201,500 | Not Implemented |
UD1053 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,508 | $19,116 | Not Implemented |
UD1053 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $103,216 | $145,725 | Not Implemented |
UD1053 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,937 | $0 | Not Implemented |
UD1053 # 05 Y:2023 | 05 | 2023 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $288,790 | $110,000 | Implemented |
UD1053 # 09 Y:2023 | 09 | 2023 | OPTIMIZE PLANT POWER FACTOR | $46,233 | $119,156 | Not Implemented |
UD1044 # 04 Y:2022 | 04 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $318 | $0 | Implemented |
UD1044 # 03 Y:2022 | 03 | 2022 | REDUCE VENTILATION AIR | $6,187 | $750 | Not Implemented |
UD1044 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,125 | $2,940 | Not Implemented |
UD1044 # 05 Y:2022 | 05 | 2022 | INSTALL OCCUPANCY SENSORS | $1,611 | $900 | Not Implemented |
UD1044 # 01 Y:2022 | 01 | 2022 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $4,822 | $0 | Not Implemented |
UD1044 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $704 | $0 | Not Implemented |
UD0993 # 03 Y:2018 | 03 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $302 | $0 | Not Implemented |
UD0993 # 04 Y:2018 | 04 | 2018 | INSTALL OCCUPANCY SENSORS | $2,531 | $2,940 | Implemented |
UD0993 # 05 Y:2018 | 05 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,977 | $9,300 | Implemented |
UD0993 # 06 Y:2018 | 06 | 2018 | COVER OPEN TANKS | $3,170 | $5,040 | Not Implemented |
UD0993 # 02 Y:2018 | 02 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $392 | $0 | Not Implemented |
UD0993 # 01 Y:2018 | 01 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $27,720 | $0 | Not Implemented |
UD0951 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $746 | $50 | Not Implemented |
UD0951 # 06 Y:2016 | 06 | 2016 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $3,332 | $3,750 | Implemented |
UD0951 # 01 Y:2016 | 01 | 2016 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,773 | $0 | Not Implemented |
UD0951 # 02 Y:2016 | 02 | 2016 | INSTALL OCCUPANCY SENSORS | $3,278 | $1,200 | Not Implemented |